Cg Living construction progress
Cg Living in Palm Deira is 1.6% built at the Land Department inspection of May 2026. Developer C G Gulf Real Estate Development. Completion registered for June 2028.
1.6%
Built, at the Land Department site inspection of 18 May 2026
Running behind its date
- Completion date (Land Department)
- June 2028
- Finish at recent pace
- August 2070
- Construction started
- June 2025
- Registered with the Land Department
- October 2025
- Developer
- C G Gulf Real Estate Development
- Community
- Palm Deira
- Units
- 116
- Escrow bank
- United Bank Limited
- Name in Arabic
- سي جي ليفينج
- Land Department project number
- 4060
- Land Department site inspections
- 2
Schedule
Between September 2025 and May 2026 the site added about 0.2 points a month. At that rate it would finish around August 2070, more than three months after the June 2028 date registered with the Land Department.
Site inspections
18 May 2026
1.6%+1.6 pts
2 September 2025
0%
Context
Palm Deira has 95 projects under construction, 22% built on average.
Own a unit in Cg Living?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Cg Living be completed?
- The completion date registered with the Dubai Land Department is June 2028. At the pace of its recent inspections the site would reach 100% around August 2070. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Cg Living is built?
- 1.6%, measured at the Land Department site inspection on 18 May 2026. The Land Department engineers have inspected the site 2 times since September 2025.
- Is Cg Living delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Cg Living?
- The registered developer is C G Gulf Real Estate Development.
- Which bank holds the escrow account for Cg Living?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.