Cg Living construction progress

Cg Living in Palm Deira is 1.6% built at the Land Department inspection of May 2026. Developer C G Gulf Real Estate Development. Completion registered for June 2028.

1.6%

Built, at the Land Department site inspection of 18 May 2026

Running behind its date

Completion date (Land Department)
June 2028
Finish at recent pace
August 2070
Construction started
June 2025
Registered with the Land Department
October 2025
Developer
C G Gulf Real Estate Development
Community
Palm Deira
Units
116
Escrow bank
United Bank Limited
Name in Arabic
سي جي ليفينج
Land Department project number
4060
Land Department site inspections
2

Schedule

Between September 2025 and May 2026 the site added about 0.2 points a month. At that rate it would finish around August 2070, more than three months after the June 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 May 2026

1.6%+1.6 pts

  • Cg Living construction site, Land Department inspection photo 1, 18 May 2026
  • Cg Living construction site, Land Department inspection photo 2, 18 May 2026
  • Cg Living construction site, Land Department inspection photo 3, 18 May 2026
  • Cg Living construction site, Land Department inspection photo 4, 18 May 2026

2 September 2025

0%

  • Cg Living construction site, Land Department inspection photo 1, 2 September 2025
  • Cg Living construction site, Land Department inspection photo 2, 2 September 2025

All 7 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Own a unit in Cg Living?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Cg Living be completed?
The completion date registered with the Dubai Land Department is June 2028. At the pace of its recent inspections the site would reach 100% around August 2070. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Cg Living is built?
1.6%, measured at the Land Department site inspection on 18 May 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Cg Living delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Cg Living?
The registered developer is C G Gulf Real Estate Development.
Which bank holds the escrow account for Cg Living?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.