Cg Living construction progress

The registered completion date for Cg Living in Palm Deira is June 2028. At the last site inspection, in May 2026, it was 1.6% built. The developer is C G Gulf Real Estate Development.

1.6%

Built, at the site inspection of 18 May 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
August 2070
Construction started
June 2025
First registered
October 2025
Developer
C G Gulf Real Estate Development
Community
Palm Deira
Units
116
Escrow bank
United Bank Limited
Name in Arabic
سي جي ليفينج
Project number
4060
Site inspections
2

Schedule

Between September 2025 and May 2026 the site added about 0.2 points a month. At that rate it would finish around August 2070, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 May 2026

1.6%+1.6 pts

  • Cg Living construction site, inspection photo 1, 18 May 2026
  • Cg Living construction site, inspection photo 2, 18 May 2026
  • Cg Living construction site, inspection photo 3, 18 May 2026
  • Cg Living construction site, inspection photo 4, 18 May 2026

2 September 2025

0%

  • Cg Living construction site, inspection photo 1, 2 September 2025
  • Cg Living construction site, inspection photo 2, 2 September 2025

All 7 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Cg Living?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cg Living handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2070. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Cg Living?
Cg Living was 1.6% built at the site inspection on 18 May 2026. The site has been inspected 2 times since September 2025. The Land Department took 7 site photos at its inspections.
Is Cg Living delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Cg Living?
The registered developer is C G Gulf Real Estate Development.
Which bank holds the escrow account for Cg Living?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.