Bonds Avenue Residences construction progress

The registered completion date for Bonds Avenue Residences in Palm Deira is December 2026. At the last site inspection, in July 2026, it was 6.8% built. The developer is Amirah Living Developer.

6.8%

Built, at the site inspection of 1 July 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
April 2036
Construction started
January 2025
First registered
November 2024
Developer
Amirah Living Developer
Community
Palm Deira
Units
75
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بوندز افينيو ريزدنس
Project number
3276
Site inspections
4

Schedule

Between November 2025 and July 2026 the site added about 0.8 points a month. At that rate it would finish around April 2036, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 July 2026

6.8%+1.9 pts

  • Bonds Avenue Residences construction site, inspection photo 1, 1 July 2026
  • Bonds Avenue Residences construction site, inspection photo 2, 1 July 2026
  • Bonds Avenue Residences construction site, inspection photo 3, 1 July 2026
  • Bonds Avenue Residences construction site, inspection photo 4, 1 July 2026

16 March 2026

4.9%+4.0 pts

  • Bonds Avenue Residences construction site, inspection photo 1, 16 March 2026
  • Bonds Avenue Residences construction site, inspection photo 2, 16 March 2026
  • Bonds Avenue Residences construction site, inspection photo 3, 16 March 2026
  • Bonds Avenue Residences construction site, inspection photo 4, 16 March 2026

17 November 2025

0.9%+0.9 pts

  • Bonds Avenue Residences construction site, inspection photo 1, 17 November 2025
  • Bonds Avenue Residences construction site, inspection photo 2, 17 November 2025
  • Bonds Avenue Residences construction site, inspection photo 3, 17 November 2025
  • Bonds Avenue Residences construction site, inspection photo 4, 17 November 2025

10 September 2024

0%

  • Bonds Avenue Residences construction site, inspection photo 1, 10 September 2024
  • Bonds Avenue Residences construction site, inspection photo 2, 10 September 2024

All 18 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Bonds Avenue Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Bonds Avenue Residences handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Bonds Avenue Residences?
Bonds Avenue Residences was 6.8% built at the site inspection on 1 July 2026. The site has been inspected 4 times since September 2024. The Land Department took 18 site photos at its inspections.
Is Bonds Avenue Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Bonds Avenue Residences?
The registered developer is Amirah Living Developer.
Which bank holds the escrow account for Bonds Avenue Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.