Bonds Avenue Residences construction progress
The registered completion date for Bonds Avenue Residences in Palm Deira is December 2026. At the last site inspection, in July 2026, it was 6.8% built. The developer is Amirah Living Developer.
6.8%
Built, at the site inspection of 1 July 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- April 2036
- Construction started
- January 2025
- First registered
- November 2024
- Developer
- Amirah Living Developer
- Community
- Palm Deira
- Units
- 75
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- بوندز افينيو ريزدنس
- Project number
- 3276
- Site inspections
- 4
Schedule
Between November 2025 and July 2026 the site added about 0.8 points a month. At that rate it would finish around April 2036, more than three months after its registered date of December 2026.
Site inspections
1 July 2026
6.8%+1.9 pts
16 March 2026
4.9%+4.0 pts
17 November 2025
0.9%+0.9 pts
10 September 2024
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Own a unit in Bonds Avenue Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Bonds Avenue Residences handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Bonds Avenue Residences?
- Bonds Avenue Residences was 6.8% built at the site inspection on 1 July 2026. The site has been inspected 4 times since September 2024. The Land Department took 18 site photos at its inspections.
- Is Bonds Avenue Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Bonds Avenue Residences?
- The registered developer is Amirah Living Developer.
- Which bank holds the escrow account for Bonds Avenue Residences?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.