Blue Marina Residence By Shakirov Developments construction progress
The registered completion date for Blue Marina Residence By Shakirov Developments in Palm Deira is October 2027. At the last site inspection, in September 2026, it was 13% built. The developer is Shakirov Developments.
13%
Built, at the site inspection of 28 September 2026
Running behind its date
- Registered completion date
- October 2027
- Finish at recent pace
- May 2032
- Construction started
- May 2025
- First registered
- October 2025
- Developer
- Shakirov Developments
- Community
- Palm Deira
- Units
- 125
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- بلو مارينا ريزيدنس باي شاكيروف دفيليبومنتس
- Project number
- 3867
- Site inspections
- 3
Schedule
Between April 2026 and September 2026 the site added about 1.3 points a month. At that rate it would finish around May 2032, more than three months after its registered date of October 2027.
Site inspections
28 September 2026
13%+7.5 pts
3 April 2026
5.9%+4.4 pts
12 September 2025
1.6%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Own a unit in Blue Marina Residence By Shakirov Developments?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Blue Marina Residence By Shakirov Developments handover date?
- The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Blue Marina Residence By Shakirov Developments?
- Blue Marina Residence By Shakirov Developments was 13% built at the site inspection on 28 September 2026. The site has been inspected 3 times since September 2025. The Land Department took 11 site photos at its inspections.
- Is Blue Marina Residence By Shakirov Developments delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
- Who is building Blue Marina Residence By Shakirov Developments?
- The registered developer is Shakirov Developments.
- Which bank holds the escrow account for Blue Marina Residence By Shakirov Developments?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.