Avida Residences construction progress

The registered completion date for Avida Residences in Palm Deira is December 2027. At the last site inspection, in August 2026, it was 6.8% built. The developer is Serene Marina Real Estate Development.

6.8%

Built, at the site inspection of 25 August 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
December 2039
Construction started
January 2026
First registered
September 2025
Developer
Serene Marina Real Estate Development
Community
Palm Deira
Units
50
Escrow bank
Commercial Bank of Dubai
Name in Arabic
أفيدا رزيدنسيس
Project number
4066
Site inspections
4

Schedule

Between September 2025 and August 2026 the site added about 0.6 points a month. At that rate it would finish around December 2039, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 August 2026

6.8%+4.9 pts

  • Avida Residences construction site, inspection photo 1, 25 August 2026
  • Avida Residences construction site, inspection photo 2, 25 August 2026
  • Avida Residences construction site, inspection photo 3, 25 August 2026
  • Avida Residences construction site, inspection photo 4, 25 August 2026

18 May 2026

1.9%+1.9 pts

  • Avida Residences construction site, inspection photo 1, 18 May 2026
  • Avida Residences construction site, inspection photo 2, 18 May 2026
  • Avida Residences construction site, inspection photo 3, 18 May 2026
  • Avida Residences construction site, inspection photo 4, 18 May 2026

13 February 2026

0%+0.0 pts

  • Avida Residences construction site, inspection photo 1, 13 February 2026
  • Avida Residences construction site, inspection photo 2, 13 February 2026

4 September 2025

0%

  • Avida Residences construction site, inspection photo 1, 4 September 2025
  • Avida Residences construction site, inspection photo 2, 4 September 2025

All 13 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Avida Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Avida Residences handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Avida Residences?
Avida Residences was 6.8% built at the site inspection on 25 August 2026. The site has been inspected 4 times since September 2025. The Land Department took 13 site photos at its inspections.
Is Avida Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Avida Residences?
The registered developer is Serene Marina Real Estate Development.
Which bank holds the escrow account for Avida Residences?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.