Skip to content

Arka Enclave Residences construction progress

The registered completion date for Arka Enclave Residences in Palm Deira is December 2027. At the last site inspection, in September 2026, it was 3.5% built. The developer is Manodev Real Estate Development.

3.5%

Built, at the site inspection of 2 September 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
September 2036
Construction started
October 2025
First registered
July 2025
Developer
Manodev Real Estate Development
Community
Palm Deira
Units
140
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
مساكن انكلاف أركا
Project number
3799
Site inspections
3

Schedule

Between April 2026 and September 2026 the site added about 0.8 points a month. At that rate it would finish around September 2036, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 September 2026

3.5%+3.5 pts

  • Arka Enclave Residences construction site, inspection photo 1, 2 September 2026
  • Arka Enclave Residences construction site, inspection photo 2, 2 September 2026
  • Arka Enclave Residences construction site, inspection photo 3, 2 September 2026
  • Arka Enclave Residences construction site, inspection photo 4, 2 September 2026

24 April 2026

0%+0.0 pts

  • Arka Enclave Residences construction site, inspection photo 1, 24 April 2026
  • Arka Enclave Residences construction site, inspection photo 2, 24 April 2026
  • Arka Enclave Residences construction site, inspection photo 3, 24 April 2026

4 June 2025

0%

  • Arka Enclave Residences construction site, inspection photo 1, 4 June 2025
  • Arka Enclave Residences construction site, inspection photo 2, 4 June 2025

All 10 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Arka Enclave Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Arka Enclave Residences handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Arka Enclave Residences?
Arka Enclave Residences was 3.5% built at the site inspection on 2 September 2026. The site has been inspected 3 times since June 2025. The Land Department took 10 site photos at its inspections.
Is Arka Enclave Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Arka Enclave Residences?
The registered developer is Manodev Real Estate Development.
Which bank holds the escrow account for Arka Enclave Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.