Aquora By Casa Vista Development construction progress
The registered completion date for Aquora By Casa Vista Development in Palm Deira is October 2028. At the last site inspection, in July 2026, it was 2.6% built. The developer is Casa Vista Development.
2.6%
Built, at the site inspection of 21 July 2026
Running behind its date
- Registered completion date
- October 2028
- Finish at recent pace
- August 2059
- Construction started
- October 2025
- First registered
- October 2025
- Developer
- Casa Vista Development
- Community
- Palm Deira
- Units
- 111
- Escrow bank
- United Bank Limited
- Name in Arabic
- اكوارا باي كاسا فيستا للتطويرش
- Project number
- 4014
- Site inspections
- 2
Schedule
Between August 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around August 2059, more than three months after its registered date of October 2028.
Site inspections
21 July 2026
2.6%+2.6 pts
26 August 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Own a unit in Aquora By Casa Vista Development?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Aquora By Casa Vista Development handover date?
- The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2059. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Aquora By Casa Vista Development?
- Aquora By Casa Vista Development was 2.6% built at the site inspection on 21 July 2026. The site has been inspected 2 times since August 2025. The Land Department took 6 site photos at its inspections.
- Is Aquora By Casa Vista Development delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
- Who is building Aquora By Casa Vista Development?
- The registered developer is Casa Vista Development.
- Which bank holds the escrow account for Aquora By Casa Vista Development?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





