Aquora By Casa Vista Development construction progress

The registered completion date for Aquora By Casa Vista Development in Palm Deira is October 2028. At the last site inspection, in July 2026, it was 2.6% built. The developer is Casa Vista Development.

2.6%

Built, at the site inspection of 21 July 2026

Running behind its date

Registered completion date
October 2028
Finish at recent pace
August 2059
Construction started
October 2025
First registered
October 2025
Developer
Casa Vista Development
Community
Palm Deira
Units
111
Escrow bank
United Bank Limited
Name in Arabic
اكوارا باي كاسا فيستا للتطويرش
Project number
4014
Site inspections
2

Schedule

Between August 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around August 2059, more than three months after its registered date of October 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 July 2026

2.6%+2.6 pts

  • Aquora By Casa Vista Development construction site, inspection photo 1, 21 July 2026
  • Aquora By Casa Vista Development construction site, inspection photo 2, 21 July 2026
  • Aquora By Casa Vista Development construction site, inspection photo 3, 21 July 2026
  • Aquora By Casa Vista Development construction site, inspection photo 4, 21 July 2026

26 August 2025

0%

  • Aquora By Casa Vista Development construction site, inspection photo 1, 26 August 2025
  • Aquora By Casa Vista Development construction site, inspection photo 2, 26 August 2025

All 6 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Aquora By Casa Vista Development?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Aquora By Casa Vista Development handover date?
The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2059. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Aquora By Casa Vista Development?
Aquora By Casa Vista Development was 2.6% built at the site inspection on 21 July 2026. The site has been inspected 2 times since August 2025. The Land Department took 6 site photos at its inspections.
Is Aquora By Casa Vista Development delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
Who is building Aquora By Casa Vista Development?
The registered developer is Casa Vista Development.
Which bank holds the escrow account for Aquora By Casa Vista Development?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.