241 Waterside construction progress

241 Waterside in Palm Deira is 0% built at the Land Department inspection of June 2026. Developer Legacy Star Real Estate Development. Completion registered for June 2028.

0%

Built, at the Land Department site inspection of 29 June 2026

Running behind its date

Completion date (Land Department)
June 2028
Finish at recent pace
December 5283
Construction started
January 2026
Registered with the Land Department
November 2025
Developer
Legacy Star Real Estate Development
Community
Palm Deira
Units
63
Escrow bank
Emirates NBD
Name in Arabic
واترسايد 241
Land Department project number
4093
Land Department site inspections
2

Schedule

Between November 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around December 5283, more than three months after the June 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 June 2026

0%+0.0 pts

  • 241 Waterside construction site, Land Department inspection photo 1, 29 June 2026
  • 241 Waterside construction site, Land Department inspection photo 2, 29 June 2026
  • 241 Waterside construction site, Land Department inspection photo 3, 29 June 2026

3 November 2025

0%

  • 241 Waterside construction site, Land Department inspection photo 1, 3 November 2025
  • 241 Waterside construction site, Land Department inspection photo 2, 3 November 2025
  • 241 Waterside construction site, Land Department inspection photo 3, 3 November 2025

All 6 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average. 241 Waterside is behind that average.

Own a unit in 241 Waterside?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will 241 Waterside be completed?
The completion date registered with the Dubai Land Department is June 2028. At the pace of its recent inspections the site would reach 100% around December 5283. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of 241 Waterside is built?
0%, measured at the Land Department site inspection on 29 June 2026. The Land Department engineers have inspected the site 2 times since November 2025.
Is 241 Waterside delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building 241 Waterside?
The registered developer is Legacy Star Real Estate Development.
Which bank holds the escrow account for 241 Waterside?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.