241 Waterside construction progress
The registered completion date for 241 Waterside in Palm Deira is June 2028. At the last site inspection, in June 2026, it was 0% built. The developer is Legacy Star Real Estate Development.
0%
Built, at the site inspection of 29 June 2026
Running behind its date
- Registered completion date
- June 2028
- Finish at recent pace
- December 5283
- Construction started
- January 2026
- First registered
- November 2025
- Developer
- Legacy Star Real Estate Development
- Community
- Palm Deira
- Units
- 63
- Escrow bank
- Emirates NBD
- Name in Arabic
- واترسايد 241
- Project number
- 4093
- Site inspections
- 2
Schedule
Between November 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around December 5283, more than three months after its registered date of June 2028.
Site inspections
29 June 2026
0%+0.0 pts
3 November 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Own a unit in 241 Waterside?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 241 Waterside handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 5283. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on 241 Waterside?
- 241 Waterside was 0% built at the site inspection on 29 June 2026. The site has been inspected 2 times since November 2025. The Land Department took 6 site photos at its inspections.
- Is 241 Waterside delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building 241 Waterside?
- The registered developer is Legacy Star Real Estate Development.
- Which bank holds the escrow account for 241 Waterside?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


