The Willows Residences construction progress
The Willows Residences in Mohammed Bin Rashid Al Maktoum District 11 is 0.7% built at the Land Department inspection of April 2026. Developer Scc Vertex Property. Completion registered for June 2027.
0.7%
Built, at the Land Department site inspection of 14 April 2026
Running behind its date
- Completion date (Land Department)
- June 2027
- Finish at recent pace
- June 2154
- Construction started
- October 2025
- Registered with the Land Department
- May 2025
- Developer
- Scc Vertex Property
- Units
- 56
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- ذا ويلوز ريزيدنسز
- Land Department project number
- 3571
- Land Department site inspections
- 2
Schedule
Between April 2025 and April 2026 the site added about 0.1 points a month. At that rate it would finish around June 2154, more than three months after the June 2027 date registered with the Land Department.
Site inspections
14 April 2026
0.7%+0.7 pts
30 April 2025
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 26% built on average.
Own a unit in The Willows Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Willows Residences be completed?
- The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around June 2154. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Willows Residences is built?
- 0.7%, measured at the Land Department site inspection on 14 April 2026. The Land Department engineers have inspected the site 2 times since April 2025.
- Is The Willows Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building The Willows Residences?
- The registered developer is Scc Vertex Property.
- Which bank holds the escrow account for The Willows Residences?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 32%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 9.8%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 35%, Due August 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.