Skip to content

The Cube Quarter Residences construction progress

The registered completion date for The Cube Quarter Residences in Mohammed Bin Rashid Al Maktoum District 11 is December 2026. At the last site inspection, in September 2026, it was 57% built. The developer is Amwaj Alkhaleej Real Estate Development.

57%

Built, at the site inspection of 15 September 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
July 2027
Construction started
October 2024
First registered
October 2024
Developer
Amwaj Alkhaleej Real Estate Development
Units
54
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
ذا كيوب كوارتر ريزيدنسز
Project number
3279
Site inspections
6

Schedule

Between December 2025 and September 2026 the site added about 4.5 points a month. At that rate it would finish around July 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 September 2026

57%+19 pts

  • The Cube Quarter Residences construction site, inspection photo 1, 15 September 2026
  • The Cube Quarter Residences construction site, inspection photo 2, 15 September 2026
  • The Cube Quarter Residences construction site, inspection photo 3, 15 September 2026
  • The Cube Quarter Residences construction site, inspection photo 4, 15 September 2026

22 April 2026

39%+20 pts

  • The Cube Quarter Residences construction site, inspection photo 1, 22 April 2026
  • The Cube Quarter Residences construction site, inspection photo 2, 22 April 2026
  • The Cube Quarter Residences construction site, inspection photo 3, 22 April 2026
  • The Cube Quarter Residences construction site, inspection photo 4, 22 April 2026

29 December 2025

19%+15 pts

  • The Cube Quarter Residences construction site, inspection photo 1, 29 December 2025
  • The Cube Quarter Residences construction site, inspection photo 2, 29 December 2025
  • The Cube Quarter Residences construction site, inspection photo 3, 29 December 2025
  • The Cube Quarter Residences construction site, inspection photo 4, 29 December 2025

8 September 2025

4.0%+1.9 pts

  • The Cube Quarter Residences construction site, inspection photo 1, 8 September 2025
  • The Cube Quarter Residences construction site, inspection photo 2, 8 September 2025
  • The Cube Quarter Residences construction site, inspection photo 3, 8 September 2025
  • The Cube Quarter Residences construction site, inspection photo 4, 8 September 2025

25 May 2025

2.1%+2.1 pts

  • The Cube Quarter Residences construction site, inspection photo 1, 25 May 2025
  • The Cube Quarter Residences construction site, inspection photo 2, 25 May 2025
  • The Cube Quarter Residences construction site, inspection photo 3, 25 May 2025
  • The Cube Quarter Residences construction site, inspection photo 4, 25 May 2025

10 September 2024

0%

  • The Cube Quarter Residences construction site, inspection photo 1, 10 September 2024
  • The Cube Quarter Residences construction site, inspection photo 2, 10 September 2024

All 34 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.

Amwaj Alkhaleej Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Cube Quarter Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Cube Quarter Residences handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Cube Quarter Residences?
The Cube Quarter Residences was 57% built at the site inspection on 15 September 2026. The site has been inspected 6 times since September 2024. The Land Department took 34 site photos at its inspections.
Is The Cube Quarter Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building The Cube Quarter Residences?
The registered developer is Amwaj Alkhaleej Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for The Cube Quarter Residences?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.