The Cube Quarter Residences construction progress
The Cube Quarter Residences in Mohammed Bin Rashid Al Maktoum District 11 is 57% built at the Land Department inspection of September 2026. Developer Amwaj Alkhaleej Real Estate Development. Completion registered for December 2026.
57%
Built, at the Land Department site inspection of 15 September 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- July 2027
- Construction started
- October 2024
- Registered with the Land Department
- October 2024
- Developer
- Amwaj Alkhaleej Real Estate Development
- Units
- 54
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- ذا كيوب كوارتر ريزيدنسز
- Land Department project number
- 3279
- Land Department site inspections
- 6
Schedule
Between December 2025 and September 2026 the site added about 4.5 points a month. At that rate it would finish around July 2027, more than three months after the December 2026 date registered with the Land Department.
Site inspections
15 September 2026
57%+19 pts
22 April 2026
39%+20 pts
29 December 2025
19%+15 pts
8 September 2025
4.0%+1.9 pts
25 May 2025
2.1%+2.1 pts
10 September 2024
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 26% built on average.
Amwaj Alkhaleej Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Cube Quarter Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Cube Quarter Residences be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Cube Quarter Residences is built?
- 57%, measured at the Land Department site inspection on 15 September 2026. The Land Department engineers have inspected the site 6 times since September 2024.
- Is The Cube Quarter Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building The Cube Quarter Residences?
- The registered developer is Amwaj Alkhaleej Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for The Cube Quarter Residences?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Gate Eleven ResidencesAlso by Amwaj Alkhaleej Real Estate Development. 31%, Due March 2028.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 32%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 9.8%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 35%, Due August 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.











.jpeg&w=3840&q=75)