The Cube Quarter Residences construction progress
The registered completion date for The Cube Quarter Residences in Mohammed Bin Rashid Al Maktoum District 11 is December 2026. At the last site inspection, in September 2026, it was 57% built. The developer is Amwaj Alkhaleej Real Estate Development.
57%
Built, at the site inspection of 15 September 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- July 2027
- Construction started
- October 2024
- First registered
- October 2024
- Developer
- Amwaj Alkhaleej Real Estate Development
- Units
- 54
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- ذا كيوب كوارتر ريزيدنسز
- Project number
- 3279
- Site inspections
- 6
Schedule
Between December 2025 and September 2026 the site added about 4.5 points a month. At that rate it would finish around July 2027, more than three months after its registered date of December 2026.
Site inspections
15 September 2026
57%+19 pts
22 April 2026
39%+20 pts
29 December 2025
19%+15 pts
8 September 2025
4.0%+1.9 pts
25 May 2025
2.1%+2.1 pts
10 September 2024
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.
Amwaj Alkhaleej Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Cube Quarter Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Cube Quarter Residences handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Cube Quarter Residences?
- The Cube Quarter Residences was 57% built at the site inspection on 15 September 2026. The site has been inspected 6 times since September 2024. The Land Department took 34 site photos at its inspections.
- Is The Cube Quarter Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building The Cube Quarter Residences?
- The registered developer is Amwaj Alkhaleej Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for The Cube Quarter Residences?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Gate Eleven ResidencesAlso by Amwaj Alkhaleej Real Estate Development. 31%, Due March 2028.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 45%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 20%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%, Due April 2026, passed.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 47%, Due August 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.