The Collection By Naser construction progress

The registered completion date for The Collection By Naser in Mohammed Bin Rashid Al Maktoum District 11 is June 2027. At the last site inspection, in July 2026, it was 0.6% built. The developer is N A S E R Real Estate Development.

0.6%

Built, at the site inspection of 1 July 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
October 2314
Construction started
May 2025
First registered
March 2025
Developer
N A S E R Real Estate Development
Units
37
Escrow bank
Emirates Islamic Bank
Name in Arabic
ذي كوليكشن من ناصر
Project number
3282
Site inspections
2

Schedule

Between September 2024 and July 2026 the site added about 0.0 points a month. At that rate it would finish around October 2314, more than three months after its registered date of June 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 July 2026

0.6%+0.6 pts

  • The Collection By Naser construction site, inspection photo 1, 1 July 2026
  • The Collection By Naser construction site, inspection photo 2, 1 July 2026
  • The Collection By Naser construction site, inspection photo 3, 1 July 2026

12 September 2024

0%

  • The Collection By Naser construction site, inspection photo 1, 12 September 2024
  • The Collection By Naser construction site, inspection photo 2, 12 September 2024

All 5 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.

Own a unit in The Collection By Naser?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Collection By Naser handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2314. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Collection By Naser?
The Collection By Naser was 0.6% built at the site inspection on 1 July 2026. The site has been inspected 2 times since September 2024. The Land Department took 5 site photos at its inspections.
Is The Collection By Naser delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building The Collection By Naser?
The registered developer is N A S E R Real Estate Development.
Which bank holds the escrow account for The Collection By Naser?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.