Knightsbridge Park construction progress

The registered completion date for Knightsbridge Park in Mohammed Bin Rashid Al Maktoum District 11 is November 2027. At the last site inspection, in August 2026, it was 11% built. The developer is Leos Sof Real Estate Development.

11%

Built, at the site inspection of 5 August 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
November 2033
Construction started
April 2025
First registered
November 2024
Developer
Leos Sof Real Estate Development
Units
66
Escrow bank
Emirates NBD
Name in Arabic
نايتس بريدج بارك
Project number
3361
Site inspections
5

Schedule

Between December 2025 and August 2026 the site added about 1.0 points a month. At that rate it would finish around November 2033, more than three months after its registered date of November 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 August 2026

11%+1.5 pts

  • Knightsbridge Park construction site, inspection photo 1, 5 August 2026
  • Knightsbridge Park construction site, inspection photo 2, 5 August 2026
  • Knightsbridge Park construction site, inspection photo 3, 5 August 2026
  • Knightsbridge Park construction site, inspection photo 4, 5 August 2026

23 June 2026

9.3%+2.1 pts

  • Knightsbridge Park construction site, inspection photo 1, 23 June 2026
  • Knightsbridge Park construction site, inspection photo 2, 23 June 2026
  • Knightsbridge Park construction site, inspection photo 3, 23 June 2026
  • Knightsbridge Park construction site, inspection photo 4, 23 June 2026

22 April 2026

7.3%+4.5 pts

  • Knightsbridge Park construction site, inspection photo 1, 22 April 2026
  • Knightsbridge Park construction site, inspection photo 2, 22 April 2026
  • Knightsbridge Park construction site, inspection photo 3, 22 April 2026
  • Knightsbridge Park construction site, inspection photo 4, 22 April 2026

10 December 2025

2.8%+2.8 pts

  • Knightsbridge Park construction site, inspection photo 1, 10 December 2025
  • Knightsbridge Park construction site, inspection photo 2, 10 December 2025
  • Knightsbridge Park construction site, inspection photo 3, 10 December 2025
  • Knightsbridge Park construction site, inspection photo 4, 10 December 2025

31 October 2024

0%

  • Knightsbridge Park construction site, inspection photo 1, 31 October 2024
  • Knightsbridge Park construction site, inspection photo 2, 31 October 2024

All 33 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.

Leos Sof Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Knightsbridge Park?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Knightsbridge Park handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Knightsbridge Park?
Knightsbridge Park was 11% built at the site inspection on 5 August 2026. The site has been inspected 5 times since October 2024. The Land Department took 33 site photos at its inspections.
Is Knightsbridge Park delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Knightsbridge Park?
The registered developer is Leos Sof Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Knightsbridge Park?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.