Knightsbridge Park construction progress

Knightsbridge Park in Mohammed Bin Rashid Al Maktoum District 11 is 11% built at the Land Department inspection of August 2026. Developer Leos Sof Real Estate Development. Completion registered for November 2027.

11%

Built, at the Land Department site inspection of 5 August 2026

Running behind its date

Completion date (Land Department)
November 2027
Finish at recent pace
November 2033
Construction started
April 2025
Registered with the Land Department
November 2024
Developer
Leos Sof Real Estate Development
Units
66
Escrow bank
Emirates NBD
Name in Arabic
نايتس بريدج بارك
Land Department project number
3361
Land Department site inspections
5

Schedule

Between December 2025 and August 2026 the site added about 1.0 points a month. At that rate it would finish around November 2033, more than three months after the November 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

5 August 2026

11%+1.5 pts

  • Knightsbridge Park construction site, Land Department inspection photo 1, 5 August 2026
  • Knightsbridge Park construction site, Land Department inspection photo 2, 5 August 2026
  • Knightsbridge Park construction site, Land Department inspection photo 3, 5 August 2026
  • Knightsbridge Park construction site, Land Department inspection photo 4, 5 August 2026

23 June 2026

9.3%+2.1 pts

  • Knightsbridge Park construction site, Land Department inspection photo 1, 23 June 2026
  • Knightsbridge Park construction site, Land Department inspection photo 2, 23 June 2026
  • Knightsbridge Park construction site, Land Department inspection photo 3, 23 June 2026
  • Knightsbridge Park construction site, Land Department inspection photo 4, 23 June 2026

22 April 2026

7.3%+4.5 pts

  • Knightsbridge Park construction site, Land Department inspection photo 1, 22 April 2026
  • Knightsbridge Park construction site, Land Department inspection photo 2, 22 April 2026
  • Knightsbridge Park construction site, Land Department inspection photo 3, 22 April 2026
  • Knightsbridge Park construction site, Land Department inspection photo 4, 22 April 2026

10 December 2025

2.8%+2.8 pts

  • Knightsbridge Park construction site, Land Department inspection photo 1, 10 December 2025
  • Knightsbridge Park construction site, Land Department inspection photo 2, 10 December 2025
  • Knightsbridge Park construction site, Land Department inspection photo 3, 10 December 2025
  • Knightsbridge Park construction site, Land Department inspection photo 4, 10 December 2025

31 October 2024

0%

  • Knightsbridge Park construction site, Land Department inspection photo 1, 31 October 2024
  • Knightsbridge Park construction site, Land Department inspection photo 2, 31 October 2024

All 33 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 26% built on average.

Leos Sof Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Knightsbridge Park?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Knightsbridge Park be completed?
The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around November 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Knightsbridge Park is built?
11%, measured at the Land Department site inspection on 5 August 2026. The Land Department engineers have inspected the site 5 times since October 2024.
Is Knightsbridge Park delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Knightsbridge Park?
The registered developer is Leos Sof Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Knightsbridge Park?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.