Knightsbridge Park construction progress
The registered completion date for Knightsbridge Park in Mohammed Bin Rashid Al Maktoum District 11 is November 2027. At the last site inspection, in August 2026, it was 11% built. The developer is Leos Sof Real Estate Development.
11%
Built, at the site inspection of 5 August 2026
Running behind its date
- Registered completion date
- November 2027
- Finish at recent pace
- November 2033
- Construction started
- April 2025
- First registered
- November 2024
- Developer
- Leos Sof Real Estate Development
- Units
- 66
- Escrow bank
- Emirates NBD
- Name in Arabic
- نايتس بريدج بارك
- Project number
- 3361
- Site inspections
- 5
Schedule
Between December 2025 and August 2026 the site added about 1.0 points a month. At that rate it would finish around November 2033, more than three months after its registered date of November 2027.
Site inspections
5 August 2026
11%+1.5 pts
23 June 2026
9.3%+2.1 pts
22 April 2026
7.3%+4.5 pts
10 December 2025
2.8%+2.8 pts
31 October 2024
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.
Leos Sof Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Knightsbridge Park?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Knightsbridge Park handover date?
- The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Knightsbridge Park?
- Knightsbridge Park was 11% built at the site inspection on 5 August 2026. The site has been inspected 5 times since October 2024. The Land Department took 33 site photos at its inspections.
- Is Knightsbridge Park delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Knightsbridge Park?
- The registered developer is Leos Sof Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Knightsbridge Park?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Knightsbridge Park 2Also by Leos Sof Real Estate Development. 0%, Due November 2027.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 45%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 20%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%, Due April 2026, passed.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 47%, Due August 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
