High Best Tower construction progress
High Best Tower in Mohammed Bin Rashid Al Maktoum District 11 was registered to complete in November 2026 and is still under construction. At the last site inspection, in May 2026, it was 91% built. The developer is True Future Real Estate Development.
91%
Built, at the site inspection of 19 May 2026
1 months past its registered completion date
- Registered completion date
- November 2026
- Finish at recent pace
- July 2026
- Construction started
- November 2024
- First registered
- March 2025
- Developer
- True Future Real Estate Development
- Units
- 88
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- البرج العالي الأفضل
- Project number
- 3493
- Site inspections
- 6
Schedule
High Best Tower was registered to complete in November 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 4.5 points a month. Kept at that rate, the site would reach 100% around July 2026.
Site inspections
19 May 2026
91%+20 pts
28 January 2026
70%+15 pts
14 October 2025
55%+17 pts
22 May 2025
38%+18 pts
13 February 2025
20%+4.4 pts
23 January 2025
16%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.
True Future Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in High Best Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the High Best Tower handover date?
- The registered completion date was November 2026, and the register still lists High Best Tower as under construction. At the pace of its recent inspections the site would reach 100% around July 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on High Best Tower?
- High Best Tower was 91% built at the site inspection on 19 May 2026. The site has been inspected 6 times since January 2025. The Land Department took 37 site photos at its inspections.
- Is High Best Tower delayed?
- Yes. Its registered completion date of November 2026 has passed and the project is still listed as under construction.
- Who is building High Best Tower?
- The registered developer is True Future Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for High Best Tower?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Future ResidenceAlso by True Future Real Estate Development. 0%, Due June 2027.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 45%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 20%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%, Due April 2026, passed.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 47%, Due August 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.