High Best Tower construction progress

High Best Tower in Mohammed Bin Rashid Al Maktoum District 11 is 91% built at the Land Department inspection of May 2026. Developer True Future Real Estate Development. Completion registered for November 2026.

91%

Built, at the Land Department site inspection of 19 May 2026

On pace for its date

Completion date (Land Department)
November 2026
Finish at recent pace
July 2026
Construction started
November 2024
Registered with the Land Department
March 2025
Developer
True Future Real Estate Development
Units
88
Escrow bank
Emirates Islamic Bank
Name in Arabic
البرج العالي الأفضل
Land Department project number
3493
Land Department site inspections
6

Schedule

Since May 2025 High Best Tower has added about 4.5 points a month. That puts 100% around July 2026, within three months of its registered completion date of November 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

19 May 2026

91%+20 pts

  • High Best Tower construction site, Land Department inspection photo 1, 19 May 2026
  • High Best Tower construction site, Land Department inspection photo 2, 19 May 2026
  • High Best Tower construction site, Land Department inspection photo 3, 19 May 2026
  • High Best Tower construction site, Land Department inspection photo 4, 19 May 2026

28 January 2026

70%+15 pts

  • High Best Tower construction site, Land Department inspection photo 1, 28 January 2026
  • High Best Tower construction site, Land Department inspection photo 2, 28 January 2026
  • High Best Tower construction site, Land Department inspection photo 3, 28 January 2026
  • High Best Tower construction site, Land Department inspection photo 4, 28 January 2026

14 October 2025

55%+17 pts

  • High Best Tower construction site, Land Department inspection photo 1, 14 October 2025
  • High Best Tower construction site, Land Department inspection photo 2, 14 October 2025
  • High Best Tower construction site, Land Department inspection photo 3, 14 October 2025
  • High Best Tower construction site, Land Department inspection photo 4, 14 October 2025

22 May 2025

38%+18 pts

  • High Best Tower construction site, Land Department inspection photo 1, 22 May 2025
  • High Best Tower construction site, Land Department inspection photo 2, 22 May 2025
  • High Best Tower construction site, Land Department inspection photo 3, 22 May 2025
  • High Best Tower construction site, Land Department inspection photo 4, 22 May 2025

13 February 2025

20%+4.4 pts

  • High Best Tower construction site, Land Department inspection photo 1, 13 February 2025
  • High Best Tower construction site, Land Department inspection photo 2, 13 February 2025
  • High Best Tower construction site, Land Department inspection photo 3, 13 February 2025
  • High Best Tower construction site, Land Department inspection photo 4, 13 February 2025

23 January 2025

16%

  • High Best Tower construction site, Land Department inspection photo 1, 23 January 2025
  • High Best Tower construction site, Land Department inspection photo 2, 23 January 2025
  • High Best Tower construction site, Land Department inspection photo 3, 23 January 2025
  • High Best Tower construction site, Land Department inspection photo 4, 23 January 2025

All 37 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 26% built on average.

True Future Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in High Best Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will High Best Tower be completed?
The completion date registered with the Dubai Land Department is November 2026. At the pace of its recent inspections the site would reach 100% around July 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of High Best Tower is built?
91%, measured at the Land Department site inspection on 19 May 2026. The Land Department engineers have inspected the site 6 times since January 2025.
Is High Best Tower delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2026.
Who is building High Best Tower?
The registered developer is True Future Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for High Best Tower?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.