High Best Tower construction progress

High Best Tower in Mohammed Bin Rashid Al Maktoum District 11 was registered to complete in November 2026 and is still under construction. At the last site inspection, in May 2026, it was 91% built. The developer is True Future Real Estate Development.

91%

Built, at the site inspection of 19 May 2026

1 months past its registered completion date

Registered completion date
November 2026
Finish at recent pace
July 2026
Construction started
November 2024
First registered
March 2025
Developer
True Future Real Estate Development
Units
88
Escrow bank
Emirates Islamic Bank
Name in Arabic
البرج العالي الأفضل
Project number
3493
Site inspections
6

Schedule

High Best Tower was registered to complete in November 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 4.5 points a month. Kept at that rate, the site would reach 100% around July 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 May 2026

91%+20 pts

  • High Best Tower construction site, inspection photo 1, 19 May 2026
  • High Best Tower construction site, inspection photo 2, 19 May 2026
  • High Best Tower construction site, inspection photo 3, 19 May 2026
  • High Best Tower construction site, inspection photo 4, 19 May 2026

28 January 2026

70%+15 pts

  • High Best Tower construction site, inspection photo 1, 28 January 2026
  • High Best Tower construction site, inspection photo 2, 28 January 2026
  • High Best Tower construction site, inspection photo 3, 28 January 2026
  • High Best Tower construction site, inspection photo 4, 28 January 2026

14 October 2025

55%+17 pts

  • High Best Tower construction site, inspection photo 1, 14 October 2025
  • High Best Tower construction site, inspection photo 2, 14 October 2025
  • High Best Tower construction site, inspection photo 3, 14 October 2025
  • High Best Tower construction site, inspection photo 4, 14 October 2025

22 May 2025

38%+18 pts

  • High Best Tower construction site, inspection photo 1, 22 May 2025
  • High Best Tower construction site, inspection photo 2, 22 May 2025
  • High Best Tower construction site, inspection photo 3, 22 May 2025
  • High Best Tower construction site, inspection photo 4, 22 May 2025

13 February 2025

20%+4.4 pts

  • High Best Tower construction site, inspection photo 1, 13 February 2025
  • High Best Tower construction site, inspection photo 2, 13 February 2025
  • High Best Tower construction site, inspection photo 3, 13 February 2025
  • High Best Tower construction site, inspection photo 4, 13 February 2025

23 January 2025

16%

  • High Best Tower construction site, inspection photo 1, 23 January 2025
  • High Best Tower construction site, inspection photo 2, 23 January 2025
  • High Best Tower construction site, inspection photo 3, 23 January 2025
  • High Best Tower construction site, inspection photo 4, 23 January 2025

All 37 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.

True Future Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in High Best Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the High Best Tower handover date?
The registered completion date was November 2026, and the register still lists High Best Tower as under construction. At the pace of its recent inspections the site would reach 100% around July 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on High Best Tower?
High Best Tower was 91% built at the site inspection on 19 May 2026. The site has been inspected 6 times since January 2025. The Land Department took 37 site photos at its inspections.
Is High Best Tower delayed?
Yes. Its registered completion date of November 2026 has passed and the project is still listed as under construction.
Who is building High Best Tower?
The registered developer is True Future Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for High Best Tower?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.