Derby Heights construction progress
The registered completion date for Derby Heights in Mohammed Bin Rashid Al Maktoum District 11 is October 2027. At the last site inspection, in September 2026, it was 10% built. The developer is A M I S Signature Development.
10%
Built, at the site inspection of 2 September 2026
Running behind its date
- Registered completion date
- October 2027
- Finish at recent pace
- November 2034
- Construction started
- February 2026
- First registered
- October 2025
- Developer
- A M I S Signature Development
- Units
- 51
- Escrow bank
- United Bank Limited
- Name in Arabic
- ديربي هايتس
- Project number
- 4131
- Site inspections
- 3
Schedule
Between September 2025 and September 2026 the site added about 0.9 points a month. At that rate it would finish around November 2034, more than three months after its registered date of October 2027.
Site inspections
2 September 2026
10%+8.0 pts
1 June 2026
2.1%+2.1 pts
30 September 2025
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.
Own a unit in Derby Heights?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Derby Heights handover date?
- The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Derby Heights?
- Derby Heights was 10% built at the site inspection on 2 September 2026. The site has been inspected 3 times since September 2025. The Land Department took 9 site photos at its inspections.
- Is Derby Heights delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
- Who is building Derby Heights?
- The registered developer is A M I S Signature Development.
- Which bank holds the escrow account for Derby Heights?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 45%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 20%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%, Due April 2026, passed.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 47%, Due August 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.