Reem By Vision construction progress
Reem By Vision in Liwan1 is 53% built at the Land Department inspection of July 2026. Developer Clear Vision Real Estate Development. Completion registered for December 2026.
53%
Built, at the Land Department site inspection of 23 July 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- May 2027
- Construction started
- May 2025
- Registered with the Land Department
- April 2025
- Developer
- Clear Vision Real Estate Development
- Community
- Liwan1
- Units
- 200
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- ريم باي فيجن
- Land Department project number
- 3612
- Land Department site inspections
- 4
Schedule
Between January 2026 and July 2026 the site added about 4.6 points a month. At that rate it would finish around May 2027, more than three months after the December 2026 date registered with the Land Department.
Site inspections
23 July 2026
53%+14 pts
28 April 2026
39%+15 pts
13 January 2026
24%+24 pts
17 March 2025
0%
Context
Liwan1 has 5 projects under construction, 30% built on average.
Clear Vision Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Reem By Vision?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Reem By Vision be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around May 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Reem By Vision is built?
- 53%, measured at the Land Department site inspection on 23 July 2026. The Land Department engineers have inspected the site 4 times since March 2025.
- Is Reem By Vision delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Reem By Vision?
- The registered developer is Clear Vision Real Estate Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Reem By Vision?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verde By VisionAlso by Clear Vision Real Estate Development. 1.6%, Due September 2027.
- Vista By VisionAlso by Clear Vision Real Estate Development. 3.4%, Due September 2027.
- Sera Gardens By VisionAlso by Clear Vision Real Estate Development. 0%.
- Albero By Oro24Nearby in Liwan1. 45%.
- Empire LakeviewsNearby in Liwan1. 2.0%.
- Alma GardensNearby in Liwan1. 50%, Due May 2026, passed.
- Symbolic AltusNearby in Liwan1. 1.3%, Due May 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.