Reem By Vision construction progress

The registered completion date for Reem By Vision in Liwan1 is December 2026. At the last site inspection, in October 2026, it was 70% built. The developer is Clear Vision Real Estate Development.

70%

Built, at the site inspection of 13 October 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
April 2027
Construction started
May 2025
First registered
April 2025
Community
Liwan1
Units
200
Escrow bank
The National Bank of Fujairah
Name in Arabic
ريم باي فيجن
Project number
3612
Site inspections
5

Schedule

Between January 2026 and October 2026 the site added about 5.1 points a month. At that rate it would finish around April 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 October 2026

70%+17 pts

  • Reem By Vision construction site, inspection photo 1, 13 October 2026
  • Reem By Vision construction site, inspection photo 2, 13 October 2026
  • Reem By Vision construction site, inspection photo 3, 13 October 2026
  • Reem By Vision construction site, inspection photo 4, 13 October 2026

23 July 2026

53%+14 pts

  • Reem By Vision construction site, inspection photo 1, 23 July 2026
  • Reem By Vision construction site, inspection photo 2, 23 July 2026
  • Reem By Vision construction site, inspection photo 3, 23 July 2026
  • Reem By Vision construction site, inspection photo 4, 23 July 2026

28 April 2026

39%+15 pts

  • Reem By Vision construction site, inspection photo 1, 28 April 2026
  • Reem By Vision construction site, inspection photo 2, 28 April 2026
  • Reem By Vision construction site, inspection photo 3, 28 April 2026
  • Reem By Vision construction site, inspection photo 4, 28 April 2026

13 January 2026

24%+24 pts

  • Reem By Vision construction site, inspection photo 1, 13 January 2026
  • Reem By Vision construction site, inspection photo 2, 13 January 2026
  • Reem By Vision construction site, inspection photo 3, 13 January 2026
  • Reem By Vision construction site, inspection photo 4, 13 January 2026

17 March 2025

0%

  • Reem By Vision construction site, inspection photo 1, 17 March 2025
  • Reem By Vision construction site, inspection photo 2, 17 March 2025

All 43 site photos, by inspection date

Context

Liwan1 has 6 projects under construction, 28% built on average.

Clear Vision Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Reem By Vision?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Reem By Vision handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Reem By Vision?
Reem By Vision was 70% built at the site inspection on 13 October 2026. The site has been inspected 5 times since March 2025. The Land Department took 43 site photos at its inspections.
Is Reem By Vision delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Reem By Vision?
The registered developer is Clear Vision Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Reem By Vision?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.