Reem By Vision construction progress

Reem By Vision in Liwan1 is 53% built at the Land Department inspection of July 2026. Developer Clear Vision Real Estate Development. Completion registered for December 2026.

53%

Built, at the Land Department site inspection of 23 July 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
May 2027
Construction started
May 2025
Registered with the Land Department
April 2025
Community
Liwan1
Units
200
Escrow bank
The National Bank of Fujairah
Name in Arabic
ريم باي فيجن
Land Department project number
3612
Land Department site inspections
4

Schedule

Between January 2026 and July 2026 the site added about 4.6 points a month. At that rate it would finish around May 2027, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 July 2026

53%+14 pts

  • Reem By Vision construction site, Land Department inspection photo 1, 23 July 2026
  • Reem By Vision construction site, Land Department inspection photo 2, 23 July 2026
  • Reem By Vision construction site, Land Department inspection photo 3, 23 July 2026
  • Reem By Vision construction site, Land Department inspection photo 4, 23 July 2026

28 April 2026

39%+15 pts

  • Reem By Vision construction site, Land Department inspection photo 1, 28 April 2026
  • Reem By Vision construction site, Land Department inspection photo 2, 28 April 2026
  • Reem By Vision construction site, Land Department inspection photo 3, 28 April 2026
  • Reem By Vision construction site, Land Department inspection photo 4, 28 April 2026

13 January 2026

24%+24 pts

  • Reem By Vision construction site, Land Department inspection photo 1, 13 January 2026
  • Reem By Vision construction site, Land Department inspection photo 2, 13 January 2026
  • Reem By Vision construction site, Land Department inspection photo 3, 13 January 2026
  • Reem By Vision construction site, Land Department inspection photo 4, 13 January 2026

17 March 2025

0%

  • Reem By Vision construction site, Land Department inspection photo 1, 17 March 2025
  • Reem By Vision construction site, Land Department inspection photo 2, 17 March 2025

All 30 site photos, by inspection date

Context

Liwan1 has 5 projects under construction, 30% built on average.

Clear Vision Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Reem By Vision?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Reem By Vision be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around May 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Reem By Vision is built?
53%, measured at the Land Department site inspection on 23 July 2026. The Land Department engineers have inspected the site 4 times since March 2025.
Is Reem By Vision delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Reem By Vision?
The registered developer is Clear Vision Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Reem By Vision?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.