Reem By Vision construction progress
The registered completion date for Reem By Vision in Liwan1 is December 2026. At the last site inspection, in October 2026, it was 70% built. The developer is Clear Vision Real Estate Development.
70%
Built, at the site inspection of 13 October 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- April 2027
- Construction started
- May 2025
- First registered
- April 2025
- Developer
- Clear Vision Real Estate Development
- Community
- Liwan1
- Units
- 200
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- ريم باي فيجن
- Project number
- 3612
- Site inspections
- 5
Schedule
Between January 2026 and October 2026 the site added about 5.1 points a month. At that rate it would finish around April 2027, more than three months after its registered date of December 2026.
Site inspections
13 October 2026
70%+17 pts
23 July 2026
53%+14 pts
28 April 2026
39%+15 pts
13 January 2026
24%+24 pts
17 March 2025
0%
Context
Liwan1 has 6 projects under construction, 28% built on average.
Clear Vision Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Reem By Vision?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Reem By Vision handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Reem By Vision?
- Reem By Vision was 70% built at the site inspection on 13 October 2026. The site has been inspected 5 times since March 2025. The Land Department took 43 site photos at its inspections.
- Is Reem By Vision delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Reem By Vision?
- The registered developer is Clear Vision Real Estate Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Reem By Vision?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verde By VisionAlso by Clear Vision Real Estate Development. 12%, Due September 2027.
- Vista By VisionAlso by Clear Vision Real Estate Development. 12%, Due September 2027.
- Sera Gardens By VisionAlso by Clear Vision Real Estate Development. 0%, Due April 2028.
- Albero By Oro24Nearby in Liwan1. 45%.
- Empire LakeviewsNearby in Liwan1. 2.0%, Due June 2028.
- Alma GardensNearby in Liwan1. 50%, Due May 2026, passed.
- Confident PrestonNearby in Liwan1. 0%, Due June 2029.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)