Alma Gardens construction progress
Alma Gardens in Liwan1 was registered to complete in May 2026 and is still under construction. At the last site inspection, in August 2026, it was 50% built. The developer is Alma Real Estate Developments.
50%
Built, at the site inspection of 18 August 2026
6 months past its registered completion date
- Registered completion date
- May 2026
- Finish at recent pace
- December 2027
- Construction started
- January 2025
- First registered
- January 2025
- Developer
- Alma Real Estate Developments
- Community
- Liwan1
- Units
- 80
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- الما غاردنز
- Project number
- 3454
- Site inspections
- 5
Schedule
Alma Gardens was registered to complete in May 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around December 2027.
Site inspections
18 August 2026
50%+15 pts
12 March 2026
35%+13 pts
18 November 2025
22%+12 pts
14 July 2025
11%+11 pts
30 December 2024
0%
Context
Liwan1 has 6 projects under construction, 28% built on average.
Own a unit in Alma Gardens?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Alma Gardens handover date?
- The registered completion date was May 2026, and the register still lists Alma Gardens as under construction. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Alma Gardens?
- Alma Gardens was 50% built at the site inspection on 18 August 2026. The site has been inspected 5 times since December 2024. The Land Department took 34 site photos at its inspections.
- Is Alma Gardens delayed?
- Yes. Its registered completion date of May 2026 has passed and the project is still listed as under construction.
- Who is building Alma Gardens?
- The registered developer is Alma Real Estate Developments.
- Which bank holds the escrow account for Alma Gardens?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Albero By Oro24Nearby in Liwan1. 45%.
- Empire LakeviewsNearby in Liwan1. 2.0%, Due June 2028.
- Reem By VisionNearby in Liwan1. 70%, Due December 2026.
- Confident PrestonNearby in Liwan1. 0%, Due June 2029.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)