Alma Gardens construction progress
Alma Gardens in Liwan1 is 50% built at the Land Department inspection of August 2026. Developer Alma Real Estate Developments. Completion registered for May 2026.
50%
Built, at the Land Department site inspection of 18 August 2026
5 months past its registered completion date
- Completion date (Land Department)
- May 2026
- Finish at recent pace
- December 2027
- Construction started
- January 2025
- Registered with the Land Department
- January 2025
- Developer
- Alma Real Estate Developments
- Community
- Liwan1
- Units
- 80
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- الما غاردنز
- Land Department project number
- 3454
- Land Department site inspections
- 5
Schedule
Alma Gardens was registered to complete in May 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around December 2027.
Site inspections
18 August 2026
50%+15 pts
12 March 2026
35%+13 pts
18 November 2025
22%+12 pts
14 July 2025
11%+11 pts
30 December 2024
0%
Context
Liwan1 has 5 projects under construction, 30% built on average.
Own a unit in Alma Gardens?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Alma Gardens be completed?
- The completion date registered with the Dubai Land Department is May 2026. At the pace of its recent inspections the site would reach 100% around December 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Alma Gardens is built?
- 50%, measured at the Land Department site inspection on 18 August 2026. The Land Department engineers have inspected the site 5 times since December 2024.
- Is Alma Gardens delayed?
- Yes. Its registered completion date of May 2026 has passed and the Land Department still lists it as under construction.
- Who is building Alma Gardens?
- The registered developer is Alma Real Estate Developments.
- Which bank holds the escrow account for Alma Gardens?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Albero By Oro24Nearby in Liwan1. 45%.
- Empire LakeviewsNearby in Liwan1. 2.0%.
- Reem By VisionNearby in Liwan1. 53%, Due December 2026.
- Symbolic AltusNearby in Liwan1. 1.3%, Due May 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)