Vista By Vision construction progress

The registered completion date for Vista By Vision is September 2027. At the last site inspection, in October 2026, it was 12% built. The developer is Clear Vision Real Estate Development.

12%

Built, at the site inspection of 12 October 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
August 2033
Construction started
January 2026
First registered
November 2025
Units
328
Escrow bank
The National Bank of Fujairah
Name in Arabic
فيستا باي فيجن
Project number
4175
Site inspections
3

Schedule

Between October 2025 and October 2026 the site added about 1.1 points a month. At that rate it would finish around August 2033, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 October 2026

12%+8.8 pts

  • Vista By Vision construction site, inspection photo 1, 12 October 2026
  • Vista By Vision construction site, inspection photo 2, 12 October 2026
  • Vista By Vision construction site, inspection photo 3, 12 October 2026
  • Vista By Vision construction site, inspection photo 4, 12 October 2026

14 May 2026

3.4%+3.4 pts

  • Vista By Vision construction site, inspection photo 1, 14 May 2026
  • Vista By Vision construction site, inspection photo 2, 14 May 2026
  • Vista By Vision construction site, inspection photo 3, 14 May 2026
  • Vista By Vision construction site, inspection photo 4, 14 May 2026

28 October 2025

0%

  • Vista By Vision construction site, inspection photo 1, 28 October 2025
  • Vista By Vision construction site, inspection photo 2, 28 October 2025

All 14 site photos, by inspection date

Context

Clear Vision Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Vista By Vision?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Vista By Vision handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Vista By Vision?
Vista By Vision was 12% built at the site inspection on 12 October 2026. The site has been inspected 3 times since October 2025. The Land Department took 14 site photos at its inspections.
Is Vista By Vision delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Vista By Vision?
The registered developer is Clear Vision Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Vista By Vision?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.