Qpoint Liwan-Plot R046 construction progress

The register lists Qpoint Liwan-Plot R046 in Liwan1 as complete, with a registered completion date of January 2017. Its last site inspection on record was in January 2017. The developer is Al Mazaya Real Estate.

100%

Built, at the site inspection of 25 January 2017

Construction complete

Registered completion date
January 2017
Construction started
March 2009
First registered
June 2009
Developer
Al Mazaya Real Estate
Community
Liwan1
Units
57
Escrow bank
Mashreq Bank
Name in Arabic
كيو بوينت ليوان -Plot R046
Project number
1198
Site inspections
12

Schedule

The register lists Qpoint Liwan-Plot R046 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2010201220142016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 January 2017

100%+18 pts

  • Qpoint Liwan-Plot R046 construction site, inspection photo 1, 25 January 2017
  • Qpoint Liwan-Plot R046 construction site, inspection photo 2, 25 January 2017
  • Qpoint Liwan-Plot R046 construction site, inspection photo 3, 25 January 2017
  • Qpoint Liwan-Plot R046 construction site, inspection photo 4, 25 January 2017

10 August 2016

82%+6.8 pts

  • Qpoint Liwan-Plot R046 construction site, inspection photo 1, 10 August 2016
  • Qpoint Liwan-Plot R046 construction site, inspection photo 2, 10 August 2016
  • Qpoint Liwan-Plot R046 construction site, inspection photo 3, 10 August 2016
  • Qpoint Liwan-Plot R046 construction site, inspection photo 4, 10 August 2016

21 March 2016

75%+17 pts

  • Qpoint Liwan-Plot R046 construction site, inspection photo 1, 21 March 2016
  • Qpoint Liwan-Plot R046 construction site, inspection photo 2, 21 March 2016
  • Qpoint Liwan-Plot R046 construction site, inspection photo 3, 21 March 2016

29 November 2015

59%+1.7 pts

  • Qpoint Liwan-Plot R046 construction site, inspection photo 1, 29 November 2015
  • Qpoint Liwan-Plot R046 construction site, inspection photo 2, 29 November 2015
  • Qpoint Liwan-Plot R046 construction site, inspection photo 3, 29 November 2015
  • Qpoint Liwan-Plot R046 construction site, inspection photo 4, 29 November 2015

1 July 2015

57%+3.9 pts

  • Qpoint Liwan-Plot R046 construction site, inspection photo 1, 1 July 2015
  • Qpoint Liwan-Plot R046 construction site, inspection photo 2, 1 July 2015
  • Qpoint Liwan-Plot R046 construction site, inspection photo 3, 1 July 2015
  • Qpoint Liwan-Plot R046 construction site, inspection photo 4, 1 July 2015

18 February 2015

53%+6.9 pts

  • Qpoint Liwan-Plot R046 construction site, inspection photo 1, 18 February 2015
  • Qpoint Liwan-Plot R046 construction site, inspection photo 2, 18 February 2015
  • Qpoint Liwan-Plot R046 construction site, inspection photo 3, 18 February 2015
  • Qpoint Liwan-Plot R046 construction site, inspection photo 4, 18 February 2015

1 November 2014

46%+0.5 pts

  • Qpoint Liwan-Plot R046 construction site, inspection photo 1, 1 November 2014
  • Qpoint Liwan-Plot R046 construction site, inspection photo 2, 1 November 2014
  • Qpoint Liwan-Plot R046 construction site, inspection photo 3, 1 November 2014
  • Qpoint Liwan-Plot R046 construction site, inspection photo 4, 1 November 2014

17 July 2014

46%

  • Qpoint Liwan-Plot R046 construction site, inspection photo 1, 17 July 2014
  • Qpoint Liwan-Plot R046 construction site, inspection photo 2, 17 July 2014
  • Qpoint Liwan-Plot R046 construction site, inspection photo 3, 17 July 2014
  • Qpoint Liwan-Plot R046 construction site, inspection photo 4, 17 July 2014

17 March 2014

46%

  • Qpoint Liwan-Plot R046 construction site, inspection photo 1, 17 March 2014
  • Qpoint Liwan-Plot R046 construction site, inspection photo 2, 17 March 2014
  • Qpoint Liwan-Plot R046 construction site, inspection photo 3, 17 March 2014

18 August 2013

46%+10 pts

  • Qpoint Liwan-Plot R046 construction site, inspection photo 1, 18 August 2013
  • Qpoint Liwan-Plot R046 construction site, inspection photo 2, 18 August 2013
  • Qpoint Liwan-Plot R046 construction site, inspection photo 3, 18 August 2013
  • Qpoint Liwan-Plot R046 construction site, inspection photo 4, 18 August 2013

All 77 site photos, by inspection date

Context

Liwan1 has 6 projects under construction, 28% built on average.

Own a unit in Qpoint Liwan-Plot R046?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Qpoint Liwan-Plot R046 handover date?
Construction of Qpoint Liwan-Plot R046 is recorded as complete, with a registered completion date of January 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Qpoint Liwan-Plot R046?
Qpoint Liwan-Plot R046 was 100% built at the site inspection on 25 January 2017. The site has been inspected 12 times since May 2012. The Land Department took 77 site photos at its inspections.
Is Qpoint Liwan-Plot R046 delayed?
The register lists construction as complete.
Who is building Qpoint Liwan-Plot R046?
The registered developer is Al Mazaya Real Estate.
Which bank holds the escrow account for Qpoint Liwan-Plot R046?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.