Qpoint Liwan-Plot R046 construction photos

77 photos from 12 site inspections, newest first. The percentage is how much of Qpoint Liwan-Plot R046 was built on the day of each visit.

25 January 2017100% built

10 August 201682% built

21 March 201675% built

29 November 201559% built

1 July 201557% built

18 February 201553% built

1 November 201446% built

17 July 201446% built

17 March 201446% built

18 August 201346% built

14 April 201335% built

1 May 201227% built

Back to Qpoint Liwan-Plot R046 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.