Marwa Views construction progress
The registered completion date for Marwa Views in Jumeirah Village Triangle is March 2027. At the last site inspection, in July 2026, it was 40% built. The developer is New World Developments.
40%
Built, at the site inspection of 14 July 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- August 2027
- Construction started
- June 2025
- First registered
- September 2026
- Developer
- New World Developments
- Community
- Jumeirah Village Triangle
- Units
- 70
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- Marwa Views
- Project number
- 3773
- Site inspections
- 2
Schedule
Between February 2026 and July 2026 the site added about 4.8 points a month. At that rate it would finish around August 2027, more than three months after its registered date of March 2027.
Site inspections
14 July 2026
40%+22 pts
26 February 2026
18%
Context
Jumeirah Village Triangle has 29 projects under construction, 27% built on average.
Own a unit in Marwa Views?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Marwa Views handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Marwa Views?
- Marwa Views was 40% built at the site inspection on 14 July 2026. The site has been inspected 2 times since February 2026. The Land Department took 11 site photos at its inspections.
- Is Marwa Views delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Marwa Views?
- The registered developer is New World Developments.
- Which bank holds the escrow account for Marwa Views?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Volga TowerNearby in Jumeirah Village Triangle. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)