Marwa Views construction progress

The registered completion date for Marwa Views in Jumeirah Village Triangle is March 2027. At the last site inspection, in July 2026, it was 40% built. The developer is New World Developments.

40%

Built, at the site inspection of 14 July 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
August 2027
Construction started
June 2025
First registered
September 2026
Developer
New World Developments
Units
70
Escrow bank
First Abu Dhabi Bank
Name in Arabic
Marwa Views
Project number
3773
Site inspections
2

Schedule

Between February 2026 and July 2026 the site added about 4.8 points a month. At that rate it would finish around August 2027, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 July 2026

40%+22 pts

  • Marwa Views construction site, inspection photo 1, 14 July 2026
  • Marwa Views construction site, inspection photo 2, 14 July 2026
  • Marwa Views construction site, inspection photo 3, 14 July 2026
  • Marwa Views construction site, inspection photo 4, 14 July 2026

26 February 2026

18%

  • Marwa Views construction site, inspection photo 1, 26 February 2026
  • Marwa Views construction site, inspection photo 2, 26 February 2026
  • Marwa Views construction site, inspection photo 3, 26 February 2026
  • Marwa Views construction site, inspection photo 4, 26 February 2026

All 11 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Own a unit in Marwa Views?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Marwa Views handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Marwa Views?
Marwa Views was 40% built at the site inspection on 14 July 2026. The site has been inspected 2 times since February 2026. The Land Department took 11 site photos at its inspections.
Is Marwa Views delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Marwa Views?
The registered developer is New World Developments.
Which bank holds the escrow account for Marwa Views?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.