Interstellar Tower construction progress

Interstellar Tower in Jumeirah Village Triangle is 0% built at the Land Department inspection of July 2026. Developer Boujee Real Estate Development. Completion registered for September 2028.

0%

Built, at the Land Department site inspection of 6 July 2026

Running behind its date

Completion date (Land Department)
September 2028
Finish at recent pace
February 4709
Construction started
February 2026
Registered with the Land Department
December 2025
Developer
Boujee Real Estate Development
Units
285
Escrow bank
Bank of Sharjah
Name in Arabic
برج انترستلر
Land Department project number
3403
Land Department site inspections
3

Schedule

Between December 2025 and July 2026 the site added about 0.0 points a month. At that rate it would finish around February 4709, more than three months after the September 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 July 2026

0%+0.0 pts

  • Interstellar Tower construction site, Land Department inspection photo 1, 6 July 2026
  • Interstellar Tower construction site, Land Department inspection photo 2, 6 July 2026
  • Interstellar Tower construction site, Land Department inspection photo 3, 6 July 2026
  • Interstellar Tower construction site, Land Department inspection photo 4, 6 July 2026

22 December 2025

0%

  • Interstellar Tower construction site, Land Department inspection photo 1, 22 December 2025
  • Interstellar Tower construction site, Land Department inspection photo 2, 22 December 2025
  • Interstellar Tower construction site, Land Department inspection photo 3, 22 December 2025
  • Interstellar Tower construction site, Land Department inspection photo 4, 22 December 2025

19 November 2024

0%

  • Interstellar Tower construction site, Land Department inspection photo 1, 19 November 2024
  • Interstellar Tower construction site, Land Department inspection photo 2, 19 November 2024

All 10 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average.

Own a unit in Interstellar Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Interstellar Tower be completed?
The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around February 4709. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Interstellar Tower is built?
0%, measured at the Land Department site inspection on 6 July 2026. The Land Department engineers have inspected the site 3 times since November 2024.
Is Interstellar Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Interstellar Tower?
The registered developer is Boujee Real Estate Development.
Which bank holds the escrow account for Interstellar Tower?
Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.