Enaya Residences construction progress

Enaya Residences in Jumeirah Village Triangle is 39% built at the Land Department inspection of May 2026. Developer Deviate For Real Estate Development. Completion registered for March 2025.

39%

Built, at the Land Department site inspection of 14 May 2026

18 months past its registered completion date

Completion date (Land Department)
March 2025
Finish at recent pace
December 2027
Construction started
January 2024
Registered with the Land Department
March 2024
Developer
Deviate For Real Estate Development
Units
61
Escrow bank
Emirates Islamic Bank
Name in Arabic
انايا ريزيدنسز
Land Department project number
2950
Land Department site inspections
3

Schedule

Enaya Residences was registered to complete in March 2025, 18 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around December 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 May 2026

39%+27 pts

  • Enaya Residences construction site, Land Department inspection photo 1, 14 May 2026
  • Enaya Residences construction site, Land Department inspection photo 2, 14 May 2026
  • Enaya Residences construction site, Land Department inspection photo 3, 14 May 2026
  • Enaya Residences construction site, Land Department inspection photo 4, 14 May 2026

25 August 2025

12%+12 pts

  • Enaya Residences construction site, Land Department inspection photo 1, 25 August 2025
  • Enaya Residences construction site, Land Department inspection photo 2, 25 August 2025
  • Enaya Residences construction site, Land Department inspection photo 3, 25 August 2025
  • Enaya Residences construction site, Land Department inspection photo 4, 25 August 2025

8 February 2024

0%

  • Enaya Residences construction site, Land Department inspection photo 1, 8 February 2024
  • Enaya Residences construction site, Land Department inspection photo 2, 8 February 2024

All 17 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average. Enaya Residences is ahead of that average.

Own a unit in Enaya Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Enaya Residences be completed?
The completion date registered with the Dubai Land Department is March 2025. At the pace of its recent inspections the site would reach 100% around December 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Enaya Residences is built?
39%, measured at the Land Department site inspection on 14 May 2026. The Land Department engineers have inspected the site 3 times since February 2024.
Is Enaya Residences delayed?
Yes. Its registered completion date of March 2025 has passed and the Land Department still lists it as under construction.
Who is building Enaya Residences?
The registered developer is Deviate For Real Estate Development.
Which bank holds the escrow account for Enaya Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.