Enaya Residences construction progress
Enaya Residences in Jumeirah Village Triangle was registered to complete in March 2025 and is still under construction. At the last site inspection, in May 2026, it was 39% built. The developer is Deviate For Real Estate Development.
39%
Built, at the site inspection of 14 May 2026
20 months past its registered completion date
- Registered completion date
- March 2025
- Finish at recent pace
- December 2027
- Construction started
- January 2024
- First registered
- March 2024
- Developer
- Deviate For Real Estate Development
- Community
- Jumeirah Village Triangle
- Units
- 61
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- انايا ريزيدنسز
- Project number
- 2950
- Site inspections
- 3
Schedule
Enaya Residences was registered to complete in March 2025, 20 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around December 2027.
Site inspections
14 May 2026
39%+27 pts
25 August 2025
12%+12 pts
8 February 2024
0%
Context
Jumeirah Village Triangle has 29 projects under construction, 27% built on average.
Own a unit in Enaya Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Enaya Residences handover date?
- The registered completion date was March 2025, and the register still lists Enaya Residences as under construction. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Enaya Residences?
- Enaya Residences was 39% built at the site inspection on 14 May 2026. The site has been inspected 3 times since February 2024. The Land Department took 17 site photos at its inspections.
- Is Enaya Residences delayed?
- Yes. Its registered completion date of March 2025 has passed and the project is still listed as under construction.
- Who is building Enaya Residences?
- The registered developer is Deviate For Real Estate Development.
- Which bank holds the escrow account for Enaya Residences?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Volga TowerNearby in Jumeirah Village Triangle. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.