Enaya Residences construction progress

Enaya Residences in Jumeirah Village Triangle was registered to complete in March 2025 and is still under construction. At the last site inspection, in May 2026, it was 39% built. The developer is Deviate For Real Estate Development.

39%

Built, at the site inspection of 14 May 2026

20 months past its registered completion date

Registered completion date
March 2025
Finish at recent pace
December 2027
Construction started
January 2024
First registered
March 2024
Developer
Deviate For Real Estate Development
Units
61
Escrow bank
Emirates Islamic Bank
Name in Arabic
انايا ريزيدنسز
Project number
2950
Site inspections
3

Schedule

Enaya Residences was registered to complete in March 2025, 20 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around December 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 May 2026

39%+27 pts

  • Enaya Residences construction site, inspection photo 1, 14 May 2026
  • Enaya Residences construction site, inspection photo 2, 14 May 2026
  • Enaya Residences construction site, inspection photo 3, 14 May 2026
  • Enaya Residences construction site, inspection photo 4, 14 May 2026

25 August 2025

12%+12 pts

  • Enaya Residences construction site, inspection photo 1, 25 August 2025
  • Enaya Residences construction site, inspection photo 2, 25 August 2025
  • Enaya Residences construction site, inspection photo 3, 25 August 2025
  • Enaya Residences construction site, inspection photo 4, 25 August 2025

8 February 2024

0%

  • Enaya Residences construction site, inspection photo 1, 8 February 2024
  • Enaya Residences construction site, inspection photo 2, 8 February 2024

All 17 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Own a unit in Enaya Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Enaya Residences handover date?
The registered completion date was March 2025, and the register still lists Enaya Residences as under construction. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Enaya Residences?
Enaya Residences was 39% built at the site inspection on 14 May 2026. The site has been inspected 3 times since February 2024. The Land Department took 17 site photos at its inspections.
Is Enaya Residences delayed?
Yes. Its registered completion date of March 2025 has passed and the project is still listed as under construction.
Who is building Enaya Residences?
The registered developer is Deviate For Real Estate Development.
Which bank holds the escrow account for Enaya Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.