Enaya Residences construction progress
Enaya Residences in Jumeirah Village Triangle is 39% built at the Land Department inspection of May 2026. Developer Deviate For Real Estate Development. Completion registered for March 2025.
39%
Built, at the Land Department site inspection of 14 May 2026
18 months past its registered completion date
- Completion date (Land Department)
- March 2025
- Finish at recent pace
- December 2027
- Construction started
- January 2024
- Registered with the Land Department
- March 2024
- Developer
- Deviate For Real Estate Development
- Community
- Jumeirah Village Triangle
- Units
- 61
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- انايا ريزيدنسز
- Land Department project number
- 2950
- Land Department site inspections
- 3
Schedule
Enaya Residences was registered to complete in March 2025, 18 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around December 2027.
Site inspections
14 May 2026
39%+27 pts
25 August 2025
12%+12 pts
8 February 2024
0%
Context
Jumeirah Village Triangle has 31 projects under construction, 28% built on average. Enaya Residences is ahead of that average.
Own a unit in Enaya Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Enaya Residences be completed?
- The completion date registered with the Dubai Land Department is March 2025. At the pace of its recent inspections the site would reach 100% around December 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Enaya Residences is built?
- 39%, measured at the Land Department site inspection on 14 May 2026. The Land Department engineers have inspected the site 3 times since February 2024.
- Is Enaya Residences delayed?
- Yes. Its registered completion date of March 2025 has passed and the Land Department still lists it as under construction.
- Who is building Enaya Residences?
- The registered developer is Deviate For Real Estate Development.
- Which bank holds the escrow account for Enaya Residences?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Altai TowerNearby in Jumeirah Village Triangle. 98%, Due January 2026, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.