Azha Millennium Residences construction progress

Azha Millennium Residences in Jumeirah Village Triangle is 30% built at the Land Department inspection of September 2026. Developer Azha J V T Residences. Completion registered for September 2027.

30%

Built, at the Land Department site inspection of 29 September 2026

Running behind its date

Completion date (Land Department)
September 2027
Finish at recent pace
June 2029
Construction started
June 2025
Registered with the Land Department
May 2025
Developer
Azha J V T Residences
Units
200
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
أزها ميلينيوم ريزيدنسز
Land Department project number
3482
Land Department site inspections
3

Schedule

Between February 2026 and September 2026 the site added about 2.2 points a month. At that rate it would finish around June 2029, more than three months after the September 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 September 2026

30%+15 pts

  • Azha Millennium Residences construction site, Land Department inspection photo 1, 29 September 2026
  • Azha Millennium Residences construction site, Land Department inspection photo 2, 29 September 2026
  • Azha Millennium Residences construction site, Land Department inspection photo 3, 29 September 2026
  • Azha Millennium Residences construction site, Land Department inspection photo 4, 29 September 2026

25 February 2026

15%+15 pts

  • Azha Millennium Residences construction site, Land Department inspection photo 1, 25 February 2026
  • Azha Millennium Residences construction site, Land Department inspection photo 2, 25 February 2026
  • Azha Millennium Residences construction site, Land Department inspection photo 3, 25 February 2026
  • Azha Millennium Residences construction site, Land Department inspection photo 4, 25 February 2026

13 January 2025

0%

  • Azha Millennium Residences construction site, Land Department inspection photo 1, 13 January 2025
  • Azha Millennium Residences construction site, Land Department inspection photo 2, 13 January 2025

All 18 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average.

Own a unit in Azha Millennium Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azha Millennium Residences be completed?
The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around June 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azha Millennium Residences is built?
30%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 3 times since January 2025.
Is Azha Millennium Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Azha Millennium Residences?
The registered developer is Azha J V T Residences.
Which bank holds the escrow account for Azha Millennium Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.