Azha Millennium Residences construction progress
Azha Millennium Residences in Jumeirah Village Triangle is 30% built at the Land Department inspection of September 2026. Developer Azha J V T Residences. Completion registered for September 2027.
30%
Built, at the Land Department site inspection of 29 September 2026
Running behind its date
- Completion date (Land Department)
- September 2027
- Finish at recent pace
- June 2029
- Construction started
- June 2025
- Registered with the Land Department
- May 2025
- Developer
- Azha J V T Residences
- Community
- Jumeirah Village Triangle
- Units
- 200
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- أزها ميلينيوم ريزيدنسز
- Land Department project number
- 3482
- Land Department site inspections
- 3
Schedule
Between February 2026 and September 2026 the site added about 2.2 points a month. At that rate it would finish around June 2029, more than three months after the September 2027 date registered with the Land Department.
Site inspections
29 September 2026
30%+15 pts
25 February 2026
15%+15 pts
13 January 2025
0%
Context
Jumeirah Village Triangle has 31 projects under construction, 28% built on average.
Own a unit in Azha Millennium Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Azha Millennium Residences be completed?
- The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around June 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Azha Millennium Residences is built?
- 30%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 3 times since January 2025.
- Is Azha Millennium Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Azha Millennium Residences?
- The registered developer is Azha J V T Residences.
- Which bank holds the escrow account for Azha Millennium Residences?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Altai TowerNearby in Jumeirah Village Triangle. 98%, Due January 2026, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.