Ashwood Residences By Skyland Horizons Real Estate Development construction progress

Ashwood Residences By Skyland Horizons Real Estate Development in Jumeirah Village Triangle is 15% built at the Land Department inspection of August 2026. Developer Skyland Horizons Real Estate Development. Completion registered for March 2027.

15%

Built, at the Land Department site inspection of 3 August 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
June 2033
Construction started
April 2025
Registered with the Land Department
June 2025
Developer
Skyland Horizons Real Estate Development
Units
153
Escrow bank
Bank of Baroda
Name in Arabic
اشوود ريزيدنسز من سكاي لاند هوريزونز للتطوير العقاري
Land Department project number
3464
Land Department site inspections
4

Schedule

Between September 2025 and August 2026 the site added about 1.0 points a month. At that rate it would finish around June 2033, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 August 2026

15%+7.0 pts

  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 1, 3 August 2026
  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 2, 3 August 2026
  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 3, 3 August 2026
  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 4, 3 August 2026

31 March 2026

7.6%+3.8 pts

  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 1, 31 March 2026
  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 2, 31 March 2026
  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 3, 31 March 2026
  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 4, 31 March 2026

23 September 2025

3.9%+3.9 pts

  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 1, 23 September 2025
  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 2, 23 September 2025
  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 3, 23 September 2025
  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 4, 23 September 2025

16 January 2025

0%

  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 1, 16 January 2025
  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 2, 16 January 2025
  • Ashwood Residences By Skyland Horizons Real Estate Development construction site, Land Department inspection photo 3, 16 January 2025

All 18 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average.

Own a unit in Ashwood Residences By Skyland Horizons Real Estate Development?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Ashwood Residences By Skyland Horizons Real Estate Development be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around June 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Ashwood Residences By Skyland Horizons Real Estate Development is built?
15%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 4 times since January 2025.
Is Ashwood Residences By Skyland Horizons Real Estate Development delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Ashwood Residences By Skyland Horizons Real Estate Development?
The registered developer is Skyland Horizons Real Estate Development.
Which bank holds the escrow account for Ashwood Residences By Skyland Horizons Real Estate Development?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.