Saba 4 construction progress

Saba 4 in Jumeirah Lakes Towers is 30% built at the Land Department inspection of July 2026. Developer Saba 4 Fzco. Completion registered for June 2027.

30%

Built, at the Land Department site inspection of 31 July 2026

Running behind its date

Completion date (Land Department)
June 2027
Finish at recent pace
April 2030
Construction started
February 2024
Registered with the Land Department
May 2024
Developer
Saba 4 Fzco
Units
547
Escrow bank
Emirates NBD
Name in Arabic
سبا 4
Land Department project number
2851
Land Department site inspections
6

Schedule

Between October 2025 and July 2026 the site added about 1.6 points a month. At that rate it would finish around April 2030, more than three months after the June 2027 date registered with the Land Department.

0%25%50%75%100%2024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

31 July 2026

30%+10 pts

  • Saba 4 construction site, Land Department inspection photo 1, 31 July 2026
  • Saba 4 construction site, Land Department inspection photo 2, 31 July 2026
  • Saba 4 construction site, Land Department inspection photo 3, 31 July 2026
  • Saba 4 construction site, Land Department inspection photo 4, 31 July 2026

20 January 2026

20%+4.8 pts

  • Saba 4 construction site, Land Department inspection photo 1, 20 January 2026
  • Saba 4 construction site, Land Department inspection photo 2, 20 January 2026
  • Saba 4 construction site, Land Department inspection photo 3, 20 January 2026
  • Saba 4 construction site, Land Department inspection photo 4, 20 January 2026

17 October 2025

16%+3.7 pts

  • Saba 4 construction site, Land Department inspection photo 1, 17 October 2025
  • Saba 4 construction site, Land Department inspection photo 2, 17 October 2025
  • Saba 4 construction site, Land Department inspection photo 3, 17 October 2025
  • Saba 4 construction site, Land Department inspection photo 4, 17 October 2025

2 July 2025

12%+6.5 pts

  • Saba 4 construction site, Land Department inspection photo 1, 2 July 2025
  • Saba 4 construction site, Land Department inspection photo 2, 2 July 2025
  • Saba 4 construction site, Land Department inspection photo 3, 2 July 2025
  • Saba 4 construction site, Land Department inspection photo 4, 2 July 2025

24 September 2024

5.3%+5.3 pts

  • Saba 4 construction site, Land Department inspection photo 1, 24 September 2024
  • Saba 4 construction site, Land Department inspection photo 2, 24 September 2024
  • Saba 4 construction site, Land Department inspection photo 3, 24 September 2024
  • Saba 4 construction site, Land Department inspection photo 4, 24 September 2024

6 December 2023

0%

  • Saba 4 construction site, Land Department inspection photo 1, 6 December 2023
  • Saba 4 construction site, Land Department inspection photo 2, 6 December 2023

All 36 site photos, by inspection date

Context

Jumeirah Lakes Towers has 8 projects under construction, 44% built on average.

Own a unit in Saba 4?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Saba 4 be completed?
The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around April 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Saba 4 is built?
30%, measured at the Land Department site inspection on 31 July 2026. The Land Department engineers have inspected the site 6 times since December 2023.
Is Saba 4 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Saba 4?
The registered developer is Saba 4 Fzco.
Which bank holds the escrow account for Saba 4?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.