Saba 4 construction progress
Saba 4 in Jumeirah Lakes Towers is 30% built at the Land Department inspection of July 2026. Developer Saba 4 Fzco. Completion registered for June 2027.
30%
Built, at the Land Department site inspection of 31 July 2026
Running behind its date
- Completion date (Land Department)
- June 2027
- Finish at recent pace
- April 2030
- Construction started
- February 2024
- Registered with the Land Department
- May 2024
- Developer
- Saba 4 Fzco
- Community
- Jumeirah Lakes Towers
- Units
- 547
- Escrow bank
- Emirates NBD
- Name in Arabic
- سبا 4
- Land Department project number
- 2851
- Land Department site inspections
- 6
Schedule
Between October 2025 and July 2026 the site added about 1.6 points a month. At that rate it would finish around April 2030, more than three months after the June 2027 date registered with the Land Department.
Site inspections
31 July 2026
30%+10 pts
20 January 2026
20%+4.8 pts
17 October 2025
16%+3.7 pts
2 July 2025
12%+6.5 pts
24 September 2024
5.3%+5.3 pts
6 December 2023
0%
Context
Jumeirah Lakes Towers has 8 projects under construction, 44% built on average.
Own a unit in Saba 4?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Saba 4 be completed?
- The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around April 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Saba 4 is built?
- 30%, measured at the Land Department site inspection on 31 July 2026. The Land Department engineers have inspected the site 6 times since December 2023.
- Is Saba 4 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Saba 4?
- The registered developer is Saba 4 Fzco.
- Which bank holds the escrow account for Saba 4?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Vue Du LacNearby in Jumeirah Lakes Towers. 0%, Due December 2026.
- Viewz 1 By DanubeNearby in Jumeirah Lakes Towers. 50%, Due June 2026, passed.
- Viewz 2 By DanubeNearby in Jumeirah Lakes Towers. 50%, Due June 2026, passed.
- Verde By SobhaNearby in Jumeirah Lakes Towers. 85%, Due June 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.






.png&w=3840&q=75)
.jpeg&w=3840&q=75)





.jpg&w=3840&q=75)