Saba 4 construction photos

36 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Saba 4 was built on the day of each visit.

31 July 202630% built

20 January 202620% built

17 October 202516% built

2 July 202512% built

24 September 20245.3% built

6 December 20230% built