Skip to content

Orra The Embankment construction progress

The register lists Orra The Embankment in Jumeirah Islands as complete, with a registered completion date of August 2023. Its last site inspection on record was in January 2026. The developer is Orra Real Estate Development.

100%

Built, at the site inspection of 29 January 2026

Construction complete

Registered completion date
August 2023
Construction started
December 2013
First registered
November 2008
Developer
Orra Real Estate Development
Units
507
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
اورا ذي امبنكمنت
Project number
360
Site inspections
26

Schedule

The register lists Orra The Embankment as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20142017202020232026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 January 2026

100%+2.2 pts

  • Orra The Embankment construction site, inspection photo 1, 29 January 2026
  • Orra The Embankment construction site, inspection photo 2, 29 January 2026
  • Orra The Embankment construction site, inspection photo 3, 29 January 2026
  • Orra The Embankment construction site, inspection photo 4, 29 January 2026

16 October 2025

98%+0.1 pts

  • Orra The Embankment construction site, inspection photo 1, 16 October 2025
  • Orra The Embankment construction site, inspection photo 2, 16 October 2025
  • Orra The Embankment construction site, inspection photo 3, 16 October 2025
  • Orra The Embankment construction site, inspection photo 4, 16 October 2025

1 July 2025

98%+2.6 pts

  • Orra The Embankment construction site, inspection photo 1, 1 July 2025
  • Orra The Embankment construction site, inspection photo 2, 1 July 2025
  • Orra The Embankment construction site, inspection photo 3, 1 July 2025
  • Orra The Embankment construction site, inspection photo 4, 1 July 2025

24 December 2024

95%+4.9 pts

  • Orra The Embankment construction site, inspection photo 1, 24 December 2024
  • Orra The Embankment construction site, inspection photo 2, 24 December 2024
  • Orra The Embankment construction site, inspection photo 3, 24 December 2024
  • Orra The Embankment construction site, inspection photo 4, 24 December 2024

17 September 2024

90%+7.1 pts

  • Orra The Embankment construction site, inspection photo 1, 17 September 2024
  • Orra The Embankment construction site, inspection photo 2, 17 September 2024
  • Orra The Embankment construction site, inspection photo 3, 17 September 2024
  • Orra The Embankment construction site, inspection photo 4, 17 September 2024

11 June 2024

83%+7.0 pts

  • Orra The Embankment construction site, inspection photo 1, 11 June 2024
  • Orra The Embankment construction site, inspection photo 2, 11 June 2024
  • Orra The Embankment construction site, inspection photo 3, 11 June 2024
  • Orra The Embankment construction site, inspection photo 4, 11 June 2024

13 February 2024

76%+5.8 pts

  • Orra The Embankment construction site, inspection photo 1, 13 February 2024
  • Orra The Embankment construction site, inspection photo 2, 13 February 2024
  • Orra The Embankment construction site, inspection photo 3, 13 February 2024
  • Orra The Embankment construction site, inspection photo 4, 13 February 2024

23 August 2023

70%+4.5 pts

  • Orra The Embankment construction site, inspection photo 1, 23 August 2023
  • Orra The Embankment construction site, inspection photo 2, 23 August 2023
  • Orra The Embankment construction site, inspection photo 3, 23 August 2023
  • Orra The Embankment construction site, inspection photo 4, 23 August 2023

4 May 2023

66%+5.7 pts

  • Orra The Embankment construction site, inspection photo 1, 4 May 2023
  • Orra The Embankment construction site, inspection photo 2, 4 May 2023
  • Orra The Embankment construction site, inspection photo 3, 4 May 2023
  • Orra The Embankment construction site, inspection photo 4, 4 May 2023

15 November 2022

60%+3.9 pts

  • Orra The Embankment construction site, inspection photo 1, 15 November 2022
  • Orra The Embankment construction site, inspection photo 2, 15 November 2022
  • Orra The Embankment construction site, inspection photo 3, 15 November 2022
  • Orra The Embankment construction site, inspection photo 4, 15 November 2022

All 240 site photos, by inspection date

Context

Jumeirah Islands has 11 projects under construction, 45% built on average.

Own a unit in Orra The Embankment?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Orra The Embankment handover date?
Construction of Orra The Embankment is recorded as complete, with a registered completion date of August 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Orra The Embankment?
Orra The Embankment was 100% built at the site inspection on 29 January 2026. The site has been inspected 26 times since October 2014. The Land Department took 240 site photos at its inspections.
Is Orra The Embankment delayed?
The register lists construction as complete.
Who is building Orra The Embankment?
The registered developer is Orra Real Estate Development.
Which bank holds the escrow account for Orra The Embankment?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.