Orra The Embankment construction progress
The register lists Orra The Embankment in Jumeirah Islands as complete, with a registered completion date of August 2023. Its last site inspection on record was in January 2026. The developer is Orra Real Estate Development.
100%
Built, at the site inspection of 29 January 2026
Construction complete
- Registered completion date
- August 2023
- Construction started
- December 2013
- First registered
- November 2008
- Developer
- Orra Real Estate Development
- Community
- Jumeirah Islands
- Units
- 507
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- اورا ذي امبنكمنت
- Project number
- 360
- Site inspections
- 26
Schedule
The register lists Orra The Embankment as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
29 January 2026
100%+2.2 pts
16 October 2025
98%+0.1 pts
1 July 2025
98%+2.6 pts
24 December 2024
95%+4.9 pts
17 September 2024
90%+7.1 pts
11 June 2024
83%+7.0 pts
13 February 2024
76%+5.8 pts
23 August 2023
70%+4.5 pts
4 May 2023
66%+5.7 pts
15 November 2022
60%+3.9 pts
Context
Jumeirah Islands has 11 projects under construction, 45% built on average.
Own a unit in Orra The Embankment?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Orra The Embankment handover date?
- Construction of Orra The Embankment is recorded as complete, with a registered completion date of August 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Orra The Embankment?
- Orra The Embankment was 100% built at the site inspection on 29 January 2026. The site has been inspected 26 times since October 2014. The Land Department took 240 site photos at its inspections.
- Is Orra The Embankment delayed?
- The register lists construction as complete.
- Who is building Orra The Embankment?
- The registered developer is Orra Real Estate Development.
- Which bank holds the escrow account for Orra The Embankment?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Wind Tower INearby in Jumeirah Islands. 75%, Due June 2023, passed.
- The Wind Tower IINearby in Jumeirah Islands. 85%, Due June 2023, passed.
- Jumeirah Heights FrondsNearby in Jumeirah Islands. 32%, Due January 2013, passed.
- Seven City JltNearby in Jumeirah Islands. 28%, Due November 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

















.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)