240 photos from 26 site inspections, newest first. The percentage is how much of Orra The Embankment was built on the day of each visit.

29 January 2026100% built

16 October 202598% built

1 July 202598% built

24 December 202495% built

17 September 202490% built

11 June 202483% built

13 February 202476% built

23 August 202370% built

4 May 202366% built

15 November 202260% built

22 July 202256% built

10 February 202250% built

27 September 202148% built

7 April 202146% built

20 January 202145% built

8 March 202041% built

18 November 201941% built

1 April 201936% built

10 October 201834% built

26 June 201830% built

2 March 201722% built

8 June 201622% built

19 August 201520% built

5 May 201517% built

5 February 201514% built

7 October 20148.7% built