The Wind Tower Ii construction progress

The Wind Tower Ii in Jumeirah Islands is 85% built at the Land Department inspection of August 2023. Developer H A B N Real Estate Development. Completion registered for June 2023.

85%

Built, at the Land Department site inspection of 10 August 2023

40 months past its registered completion date

Completion date (Land Department)
June 2023
Finish at recent pace
July 2027
Construction started
June 2004
Registered with the Land Department
November 2008
Developer
H A B N Real Estate Development
Units
412
Escrow bank
Emirates Islamic Bank
Name in Arabic
وند تاور Ii
Land Department project number
399
Land Department site inspections
9

Schedule

The Wind Tower Ii was registered to complete in June 2023, 40 months ago, and is still under construction. Over the last year of inspections it has added about 0.3 points a month. Kept at that rate, the site would reach 100% around July 2027.

0%25%50%75%100%20052009201320172021
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 August 2023

85%+4.5 pts

  • The Wind Tower Ii construction site, Land Department inspection photo 1, 10 August 2023
  • The Wind Tower Ii construction site, Land Department inspection photo 2, 10 August 2023
  • The Wind Tower Ii construction site, Land Department inspection photo 3, 10 August 2023
  • The Wind Tower Ii construction site, Land Department inspection photo 4, 10 August 2023

16 June 2022

80%+5.4 pts

  • The Wind Tower Ii construction site, Land Department inspection photo 1, 16 June 2022
  • The Wind Tower Ii construction site, Land Department inspection photo 2, 16 June 2022
  • The Wind Tower Ii construction site, Land Department inspection photo 3, 16 June 2022
  • The Wind Tower Ii construction site, Land Department inspection photo 4, 16 June 2022

9 September 2020

75%+2.1 pts

  • The Wind Tower Ii construction site, Land Department inspection photo 1, 9 September 2020
  • The Wind Tower Ii construction site, Land Department inspection photo 2, 9 September 2020
  • The Wind Tower Ii construction site, Land Department inspection photo 3, 9 September 2020
  • The Wind Tower Ii construction site, Land Department inspection photo 4, 9 September 2020

12 June 2017

72%

  • The Wind Tower Ii construction site, Land Department inspection photo 1, 12 June 2017
  • The Wind Tower Ii construction site, Land Department inspection photo 2, 12 June 2017

9 October 2016

72%+1.7 pts

  • The Wind Tower Ii construction site, Land Department inspection photo 1, 9 October 2016
  • The Wind Tower Ii construction site, Land Department inspection photo 2, 9 October 2016
  • The Wind Tower Ii construction site, Land Department inspection photo 3, 9 October 2016
  • The Wind Tower Ii construction site, Land Department inspection photo 4, 9 October 2016

30 December 2015

71%+2.8 pts

  • The Wind Tower Ii construction site, Land Department inspection photo 1, 30 December 2015
  • The Wind Tower Ii construction site, Land Department inspection photo 2, 30 December 2015
  • The Wind Tower Ii construction site, Land Department inspection photo 3, 30 December 2015
  • The Wind Tower Ii construction site, Land Department inspection photo 4, 30 December 2015

10 March 2015

68%+10.0 pts

  • The Wind Tower Ii construction site, Land Department inspection photo 1, 10 March 2015
  • The Wind Tower Ii construction site, Land Department inspection photo 2, 10 March 2015
  • The Wind Tower Ii construction site, Land Department inspection photo 3, 10 March 2015
  • The Wind Tower Ii construction site, Land Department inspection photo 4, 10 March 2015

30 October 2014

58%+30 pts

  • The Wind Tower Ii construction site, Land Department inspection photo 1, 30 October 2014
  • The Wind Tower Ii construction site, Land Department inspection photo 2, 30 October 2014
  • The Wind Tower Ii construction site, Land Department inspection photo 3, 30 October 2014
  • The Wind Tower Ii construction site, Land Department inspection photo 4, 30 October 2014

9 April 2014

28%

  • The Wind Tower Ii construction site, Land Department inspection photo 1, 9 April 2014
  • The Wind Tower Ii construction site, Land Department inspection photo 2, 9 April 2014
  • The Wind Tower Ii construction site, Land Department inspection photo 3, 9 April 2014
  • The Wind Tower Ii construction site, Land Department inspection photo 4, 9 April 2014

All 73 site photos, by inspection date

Context

Jumeirah Islands has 11 projects under construction, 43% built on average.

H A B N Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in The Wind Tower Ii?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Wind Tower Ii be completed?
The completion date registered with the Dubai Land Department is June 2023. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Wind Tower Ii is built?
85%, measured at the Land Department site inspection on 10 August 2023. The Land Department engineers have inspected the site 9 times since April 2014.
Is The Wind Tower Ii delayed?
Yes. Its registered completion date of June 2023 has passed and the Land Department still lists it as under construction.
Who is building The Wind Tower Ii?
The registered developer is H A B N Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for The Wind Tower Ii?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.