The Wind Tower I construction progress
The Wind Tower I in Jumeirah Islands is 75% built at the Land Department inspection of August 2023. Developer H A B N Real Estate Development. Completion registered for June 2023.
75%
Built, at the Land Department site inspection of 10 August 2023
40 months past its registered completion date
- Completion date (Land Department)
- June 2023
- Finish at recent pace
- October 2038
- Construction started
- June 2003
- Registered with the Land Department
- November 2008
- Developer
- H A B N Real Estate Development
- Community
- Jumeirah Islands
- Units
- 519
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- وند تاور I
- Land Department project number
- 398
- Land Department site inspections
- 9
Schedule
The Wind Tower I was registered to complete in June 2023, 40 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around October 2038.
Site inspections
10 August 2023
75%+1.9 pts
16 June 2022
73%+2.5 pts
9 September 2020
70%
12 June 2017
71%
9 October 2016
71%+1.9 pts
30 December 2015
69%+3.4 pts
10 March 2015
66%+8.7 pts
29 October 2014
57%+27 pts
9 April 2014
30%
Context
Jumeirah Islands has 11 projects under construction, 43% built on average.
H A B N Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in The Wind Tower I?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Wind Tower I be completed?
- The completion date registered with the Dubai Land Department is June 2023. At the pace of its recent inspections the site would reach 100% around October 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Wind Tower I is built?
- 75%, measured at the Land Department site inspection on 10 August 2023. The Land Department engineers have inspected the site 9 times since April 2014.
- Is The Wind Tower I delayed?
- Yes. Its registered completion date of June 2023 has passed and the Land Department still lists it as under construction.
- Who is building The Wind Tower I?
- The registered developer is H A B N Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for The Wind Tower I?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Wind Tower IiAlso by H A B N Real Estate Development. 85%, Due June 2023, passed.
- Jumeirah Heights FrondsNearby in Jumeirah Islands. 32%, Due January 2013, passed.
- Seven City JltNearby in Jumeirah Islands. 28%, Due November 2025, passed.
- Hilton Residences Dubai Jumeirah Lakes TowersNearby in Jumeirah Islands. 63%.
- Me Do Re 2Nearby in Jumeirah Islands. 98%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)