Me Do Re 2 construction progress

Me Do Re 2 in Jumeirah Islands is 98% built at the Land Department inspection of March 2026. Developer Me Do Re Developments Dmcc. Completion registered for December 2025.

98%

Built, at the Land Department site inspection of 9 March 2026

9 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
December 2026
Construction started
October 2020
Registered with the Land Department
June 2024
Developer
Me Do Re Developments Dmcc
Units
407
Escrow bank
Commercial Bank of Dubai
Name in Arabic
مي دو ري 2
Land Department project number
3056
Land Department site inspections
3

Schedule

Me Do Re 2 was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 0.2 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%202120232025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 March 2026

98%+2.3 pts

  • Me Do Re 2 construction site, Land Department inspection photo 1, 9 March 2026
  • Me Do Re 2 construction site, Land Department inspection photo 2, 9 March 2026
  • Me Do Re 2 construction site, Land Department inspection photo 3, 9 March 2026
  • Me Do Re 2 construction site, Land Department inspection photo 4, 9 March 2026

20 May 2025

95%+15 pts

  • Me Do Re 2 construction site, Land Department inspection photo 1, 20 May 2025
  • Me Do Re 2 construction site, Land Department inspection photo 2, 20 May 2025
  • Me Do Re 2 construction site, Land Department inspection photo 3, 20 May 2025
  • Me Do Re 2 construction site, Land Department inspection photo 4, 20 May 2025

1 May 2024

81%

  • Me Do Re 2 construction site, Land Department inspection photo 1, 1 May 2024
  • Me Do Re 2 construction site, Land Department inspection photo 2, 1 May 2024
  • Me Do Re 2 construction site, Land Department inspection photo 3, 1 May 2024
  • Me Do Re 2 construction site, Land Department inspection photo 4, 1 May 2024

All 21 site photos, by inspection date

Context

Jumeirah Islands has 11 projects under construction, 43% built on average.

Own a unit in Me Do Re 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Me Do Re 2 be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Me Do Re 2 is built?
98%, measured at the Land Department site inspection on 9 March 2026. The Land Department engineers have inspected the site 3 times since May 2024.
Is Me Do Re 2 delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Me Do Re 2?
The registered developer is Me Do Re Developments Dmcc.
Which bank holds the escrow account for Me Do Re 2?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.