Me Do Re 2 construction progress

Me Do Re 2 in Jumeirah Islands was registered to complete in December 2025 and is still under construction. At the last site inspection, in October 2026, it was 98% built. The developer is Me Do Re Developments Dmcc.

98%

Built, at the site inspection of 28 October 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
June 2031
Construction started
October 2020
First registered
June 2024
Developer
Me Do Re Developments Dmcc
Units
407
Escrow bank
Commercial Bank of Dubai
Name in Arabic
مي دو ري 2
Project number
3056
Site inspections
4

Schedule

Me Do Re 2 was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 0.0 points a month. Kept at that rate, the site would reach 100% around June 2031.

0%25%50%75%100%202120232025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

98%+0.3 pts

  • Me Do Re 2 construction site, inspection photo 1, 28 October 2026
  • Me Do Re 2 construction site, inspection photo 2, 28 October 2026
  • Me Do Re 2 construction site, inspection photo 3, 28 October 2026
  • Me Do Re 2 construction site, inspection photo 4, 28 October 2026

9 March 2026

98%+2.3 pts

  • Me Do Re 2 construction site, inspection photo 1, 9 March 2026
  • Me Do Re 2 construction site, inspection photo 2, 9 March 2026
  • Me Do Re 2 construction site, inspection photo 3, 9 March 2026
  • Me Do Re 2 construction site, inspection photo 4, 9 March 2026

20 May 2025

95%+15 pts

  • Me Do Re 2 construction site, inspection photo 1, 20 May 2025
  • Me Do Re 2 construction site, inspection photo 2, 20 May 2025
  • Me Do Re 2 construction site, inspection photo 3, 20 May 2025
  • Me Do Re 2 construction site, inspection photo 4, 20 May 2025

1 May 2024

81%

  • Me Do Re 2 construction site, inspection photo 1, 1 May 2024
  • Me Do Re 2 construction site, inspection photo 2, 1 May 2024
  • Me Do Re 2 construction site, inspection photo 3, 1 May 2024
  • Me Do Re 2 construction site, inspection photo 4, 1 May 2024

All 28 site photos, by inspection date

Context

Jumeirah Islands has 11 projects under construction, 45% built on average.

Own a unit in Me Do Re 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Me Do Re 2 handover date?
The registered completion date was December 2025, and the register still lists Me Do Re 2 as under construction. At the pace of its recent inspections the site would reach 100% around June 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Me Do Re 2?
Me Do Re 2 was 98% built at the site inspection on 28 October 2026. The site has been inspected 4 times since May 2024. The Land Department took 28 site photos at its inspections.
Is Me Do Re 2 delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building Me Do Re 2?
The registered developer is Me Do Re Developments Dmcc.
Which bank holds the escrow account for Me Do Re 2?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.