Me Do Re 2 construction progress
Me Do Re 2 in Jumeirah Islands is 98% built at the Land Department inspection of March 2026. Developer Me Do Re Developments Dmcc. Completion registered for December 2025.
98%
Built, at the Land Department site inspection of 9 March 2026
9 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- December 2026
- Construction started
- October 2020
- Registered with the Land Department
- June 2024
- Developer
- Me Do Re Developments Dmcc
- Community
- Jumeirah Islands
- Units
- 407
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- مي دو ري 2
- Land Department project number
- 3056
- Land Department site inspections
- 3
Schedule
Me Do Re 2 was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 0.2 points a month. Kept at that rate, the site would reach 100% around December 2026.
Site inspections
9 March 2026
98%+2.3 pts
20 May 2025
95%+15 pts
1 May 2024
81%
Context
Jumeirah Islands has 11 projects under construction, 43% built on average.
Own a unit in Me Do Re 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Me Do Re 2 be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Me Do Re 2 is built?
- 98%, measured at the Land Department site inspection on 9 March 2026. The Land Department engineers have inspected the site 3 times since May 2024.
- Is Me Do Re 2 delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Me Do Re 2?
- The registered developer is Me Do Re Developments Dmcc.
- Which bank holds the escrow account for Me Do Re 2?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Wind Tower INearby in Jumeirah Islands. 75%, Due June 2023, passed.
- The Wind Tower IiNearby in Jumeirah Islands. 85%, Due June 2023, passed.
- Jumeirah Heights FrondsNearby in Jumeirah Islands. 32%, Due January 2013, passed.
- Seven City JltNearby in Jumeirah Islands. 28%, Due November 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.