Val By Kasco construction photos

43 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Val By Kasco was built on the day of each visit.

19 August 202673% built

6 May 202657% built

30 January 202641% built

31 October 202526% built

2 June 202513% built

14 February 20257.2% built

19 June 20240% built

Back to Val By Kasco construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.