Soul By Vision construction progress
The registered completion date for Soul By Vision in International Media Production Zone is December 2026. At the last site inspection, in October 2026, it was 77% built. The developer is Vision Platinum Real Estate Development.
77%
Built, at the site inspection of 12 October 2026
On pace for its date
- Registered completion date
- December 2026
- Finish at recent pace
- February 2027
- Construction started
- May 2025
- First registered
- May 2025
- Developer
- Vision Platinum Real Estate Development
- Community
- International Media Production Zone
- Units
- 176
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- سول باي فيجن
- Project number
- 3680
- Site inspections
- 5
Schedule
Since January 2026 Soul By Vision has added about 5.2 points a month. That puts 100% around February 2027, within three months of its registered completion date of December 2026.
Site inspections
12 October 2026
77%+15 pts
17 July 2026
62%+21 pts
17 April 2026
41%+11 pts
13 January 2026
30%+30 pts
16 April 2025
0%
Context
International Media Production Zone has 15 projects under construction, 23% built on average.
Own a unit in Soul By Vision?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Soul By Vision handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Soul By Vision?
- Soul By Vision was 77% built at the site inspection on 12 October 2026. The site has been inspected 5 times since April 2025. The Land Department took 40 site photos at its inspections.
- Is Soul By Vision delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
- Who is building Soul By Vision?
- The registered developer is Vision Platinum Real Estate Development.
- Which bank holds the escrow account for Soul By Vision?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana PortofinoNearby in International Media Production Zone. 60%.
- Samana ResortsNearby in International Media Production Zone. 5.9%, Due May 2028.
- Samana Lake ViewsNearby in International Media Production Zone. 23%.
- Samana Lake Views 2Nearby in International Media Production Zone. 12%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)