Glorious Central Residences construction progress

The register lists Glorious Central Residences in International City Phase 3 as complete, with a registered completion date of November 2025. Its last site inspection on record was in December 2025. The developer is Glorious Future Real Estate Development.

100%

Built, at the site inspection of 15 December 2025

Construction complete

Registered completion date
November 2025
Construction started
March 2024
First registered
January 2025
Developer
Glorious Future Real Estate Development
Units
151
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ريزيدينسز سنترال مجلل
Project number
3355
Site inspections
3

Schedule

The register lists Glorious Central Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 December 2025

100%+13 pts

  • Glorious Central Residences construction site, inspection photo 1, 15 December 2025
  • Glorious Central Residences construction site, inspection photo 2, 15 December 2025
  • Glorious Central Residences construction site, inspection photo 3, 15 December 2025
  • Glorious Central Residences construction site, inspection photo 4, 15 December 2025

24 March 2025

87%+30 pts

  • Glorious Central Residences construction site, inspection photo 1, 24 March 2025
  • Glorious Central Residences construction site, inspection photo 2, 24 March 2025
  • Glorious Central Residences construction site, inspection photo 3, 24 March 2025
  • Glorious Central Residences construction site, inspection photo 4, 24 March 2025

6 November 2024

57%

  • Glorious Central Residences construction site, inspection photo 1, 6 November 2024
  • Glorious Central Residences construction site, inspection photo 2, 6 November 2024
  • Glorious Central Residences construction site, inspection photo 3, 6 November 2024
  • Glorious Central Residences construction site, inspection photo 4, 6 November 2024

All 27 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Own a unit in Glorious Central Residences?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Glorious Central Residences handover date?
Construction of Glorious Central Residences is recorded as complete, with a registered completion date of November 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Glorious Central Residences?
Glorious Central Residences was 100% built at the site inspection on 15 December 2025. The site has been inspected 3 times since November 2024. The Land Department took 27 site photos at its inspections.
Is Glorious Central Residences delayed?
The register lists construction as complete.
Who is building Glorious Central Residences?
The registered developer is Glorious Future Real Estate Development.
Which bank holds the escrow account for Glorious Central Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.