4b Living construction progress

The register lists 4b Living in International City Phase 3 as complete, with a registered completion date of August 2025. Its last site inspection on record was in September 2026. The developer is H S E Realty Real Estate.

100%

Built, at the site inspection of 15 September 2026

Construction complete

Registered completion date
August 2025
Construction started
May 2024
First registered
November 2024
Developer
H S E Realty Real Estate
Units
74
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
4b ليفينج
Project number
3089
Site inspections
5

Schedule

The register lists 4b Living as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 September 2026

100%+9.0 pts

  • 4b Living construction site, inspection photo 1, 15 September 2026
  • 4b Living construction site, inspection photo 2, 15 September 2026
  • 4b Living construction site, inspection photo 3, 15 September 2026
  • 4b Living construction site, inspection photo 4, 15 September 2026

4 February 2026

91%+22 pts

  • 4b Living construction site, inspection photo 1, 4 February 2026
  • 4b Living construction site, inspection photo 2, 4 February 2026
  • 4b Living construction site, inspection photo 3, 4 February 2026
  • 4b Living construction site, inspection photo 4, 4 February 2026

14 October 2025

69%+20 pts

  • 4b Living construction site, inspection photo 1, 14 October 2025
  • 4b Living construction site, inspection photo 2, 14 October 2025
  • 4b Living construction site, inspection photo 3, 14 October 2025
  • 4b Living construction site, inspection photo 4, 14 October 2025

18 June 2025

48%+28 pts

  • 4b Living construction site, inspection photo 1, 18 June 2025
  • 4b Living construction site, inspection photo 2, 18 June 2025
  • 4b Living construction site, inspection photo 3, 18 June 2025
  • 4b Living construction site, inspection photo 4, 18 June 2025

15 October 2024

20%

  • 4b Living construction site, inspection photo 1, 15 October 2024
  • 4b Living construction site, inspection photo 2, 15 October 2024
  • 4b Living construction site, inspection photo 3, 15 October 2024
  • 4b Living construction site, inspection photo 4, 15 October 2024

All 48 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Own a unit in 4b Living?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the 4b Living handover date?
Construction of 4b Living is recorded as complete, with a registered completion date of August 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on 4b Living?
4b Living was 100% built at the site inspection on 15 September 2026. The site has been inspected 5 times since October 2024. The Land Department took 48 site photos at its inspections.
Is 4b Living delayed?
The register lists construction as complete.
Who is building 4b Living?
The registered developer is H S E Realty Real Estate.
Which bank holds the escrow account for 4b Living?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.