Tabeer 1 construction progress

The register lists Tabeer 1 in International City Phase 1 as complete, with a registered completion date of June 2022. Its last site inspection on record was in August 2022. The developer is Tabeer Real Estate Development.

100%

Built, at the site inspection of 18 August 2022

Construction complete

Registered completion date
June 2022
Construction started
January 2018
First registered
January 2019
Units
107
Escrow bank
Mashreq Bank
Name in Arabic
تعبير 1
Project number
2090
Site inspections
6

Schedule

The register lists Tabeer 1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 August 2022

100%+9.8 pts

  • Tabeer 1 construction site, inspection photo 1, 18 August 2022
  • Tabeer 1 construction site, inspection photo 2, 18 August 2022
  • Tabeer 1 construction site, inspection photo 3, 18 August 2022
  • Tabeer 1 construction site, inspection photo 4, 18 August 2022

15 December 2021

90%+17 pts

  • Tabeer 1 construction site, inspection photo 1, 15 December 2021
  • Tabeer 1 construction site, inspection photo 2, 15 December 2021
  • Tabeer 1 construction site, inspection photo 3, 15 December 2021
  • Tabeer 1 construction site, inspection photo 4, 15 December 2021

25 July 2021

73%+18 pts

  • Tabeer 1 construction site, inspection photo 1, 25 July 2021
  • Tabeer 1 construction site, inspection photo 2, 25 July 2021
  • Tabeer 1 construction site, inspection photo 3, 25 July 2021
  • Tabeer 1 construction site, inspection photo 4, 25 July 2021

15 February 2021

55%+12 pts

  • Tabeer 1 construction site, inspection photo 1, 15 February 2021
  • Tabeer 1 construction site, inspection photo 2, 15 February 2021
  • Tabeer 1 construction site, inspection photo 3, 15 February 2021
  • Tabeer 1 construction site, inspection photo 4, 15 February 2021

10 August 2020

43%+17 pts

  • Tabeer 1 construction site, inspection photo 1, 10 August 2020
  • Tabeer 1 construction site, inspection photo 2, 10 August 2020
  • Tabeer 1 construction site, inspection photo 3, 10 August 2020
  • Tabeer 1 construction site, inspection photo 4, 10 August 2020

30 September 2018

26%

  • Tabeer 1 construction site, inspection photo 1, 30 September 2018
  • Tabeer 1 construction site, inspection photo 2, 30 September 2018
  • Tabeer 1 construction site, inspection photo 3, 30 September 2018
  • Tabeer 1 construction site, inspection photo 4, 30 September 2018

All 60 site photos, by inspection date

Context

International City Phase 1 has 3 projects under construction, 46% built on average.

Tabeer Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Tabeer 1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Tabeer 1 handover date?
Construction of Tabeer 1 is recorded as complete, with a registered completion date of June 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Tabeer 1?
Tabeer 1 was 100% built at the site inspection on 18 August 2022. The site has been inspected 6 times since September 2018. The Land Department took 60 site photos at its inspections.
Is Tabeer 1 delayed?
The register lists construction as complete.
Who is building Tabeer 1?
The registered developer is Tabeer Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Tabeer 1?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.