Windsor House Ii construction progress

Windsor House Ii is 0.6% built at the Land Department inspection of August 2026. Developer Ellington Properties Development. Completion registered for July 2029.

0.6%

Built, at the Land Department site inspection of 20 August 2026

Running behind its date

Completion date (Land Department)
July 2029
Finish at recent pace
December 2135
Construction started
February 2026
Registered with the Land Department
February 2026
Units
424
Escrow bank
Mashreq Bank
Name in Arabic
Ii ويندسور هاوس
Land Department project number
4300
Land Department site inspections
2

Schedule

Between December 2025 and August 2026 the site added about 0.1 points a month. At that rate it would finish around December 2135, more than three months after the July 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 August 2026

0.6%+0.6 pts

  • Windsor House Ii construction site, Land Department inspection photo 1, 20 August 2026
  • Windsor House Ii construction site, Land Department inspection photo 2, 20 August 2026
  • Windsor House Ii construction site, Land Department inspection photo 3, 20 August 2026
  • Windsor House Ii construction site, Land Department inspection photo 4, 20 August 2026

22 December 2025

0%

  • Windsor House Ii construction site, Land Department inspection photo 1, 22 December 2025
  • Windsor House Ii construction site, Land Department inspection photo 2, 22 December 2025

All 6 site photos, by inspection date

Context

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Windsor House Ii?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Windsor House Ii be completed?
The completion date registered with the Dubai Land Department is July 2029. At the pace of its recent inspections the site would reach 100% around December 2135. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Windsor House Ii is built?
0.6%, measured at the Land Department site inspection on 20 August 2026. The Land Department engineers have inspected the site 2 times since December 2025.
Is Windsor House Ii delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2029.
Who is building Windsor House Ii?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Windsor House Ii?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.