Windsor House II construction progress

The registered completion date for Windsor House II is July 2029. At the last site inspection, in August 2026, it was 0.6% built. The developer is Ellington Properties Development.

0.6%

Built, at the site inspection of 20 August 2026

Running behind its date

Registered completion date
July 2029
Finish at recent pace
December 2135
Construction started
February 2026
First registered
February 2026
Units
424
Escrow bank
Mashreq Bank
Name in Arabic
Ii ويندسور هاوس
Project number
4300
Site inspections
2

Schedule

Between December 2025 and August 2026 the site added about 0.1 points a month. At that rate it would finish around December 2135, more than three months after its registered date of July 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 August 2026

0.6%+0.6 pts

  • Windsor House II construction site, inspection photo 1, 20 August 2026
  • Windsor House II construction site, inspection photo 2, 20 August 2026
  • Windsor House II construction site, inspection photo 3, 20 August 2026
  • Windsor House II construction site, inspection photo 4, 20 August 2026

22 December 2025

0%

  • Windsor House II construction site, inspection photo 1, 22 December 2025
  • Windsor House II construction site, inspection photo 2, 22 December 2025

All 6 site photos, by inspection date

Context

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Windsor House II?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Windsor House II handover date?
The registered completion date is July 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2135. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Windsor House II?
Windsor House II was 0.6% built at the site inspection on 20 August 2026. The site has been inspected 2 times since December 2025. The Land Department took 6 site photos at its inspections.
Is Windsor House II delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2029.
Who is building Windsor House II?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Windsor House II?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.