The Woods construction progress
The registered completion date for The Woods is December 2030. At the last site inspection, in May 2026, it was 0% built. The developer is Sobha.
0%
Built, at the site inspection of 21 May 2026
- Registered completion date
- December 2030
- Construction started
- December 2026
- First registered
- July 2026
- Developer
- Sobha
- Units
- 1,267
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- ذا وودز
- Project number
- 4485
- Site inspections
- 1
Schedule
The Woods has one site inspection on record so far, which is not enough to measure a pace. A pace needs two inspections at least a month apart.
Site inspections
21 May 2026
0%
Context
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Woods?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Woods handover date?
- The registered completion date is December 2030. Handover of units starts once construction is complete, on the developer's schedule. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Woods?
- The Woods was 0% built at the site inspection on 21 May 2026. The Land Department took 4 site photos at its inspections.
- Who is building The Woods?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for The Woods?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 45%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vista HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.