Sobha Central construction progress

The registered completion date for Sobha Central is December 2031. At the last site inspection, in September 2026, it was 2.4% built. The developer is Sobha.

2.4%

Built, at the site inspection of 29 September 2026

Running behind its date

Registered completion date
December 2031
Finish at recent pace
June 2055
Construction started
March 2026
First registered
March 2026
Developer
Sobha
Units
2,169
Escrow bank
Dubai Islamic Bank
Name in Arabic
شوبا سنترال
Project number
4328
Site inspections
2

Schedule

Between January 2026 and September 2026 the site added about 0.3 points a month. At that rate it would finish around June 2055, more than three months after its registered date of December 2031.

0%25%50%75%100%20272028202920302031
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 September 2026

2.4%+2.4 pts

  • Sobha Central construction site, inspection photo 1, 29 September 2026
  • Sobha Central construction site, inspection photo 2, 29 September 2026
  • Sobha Central construction site, inspection photo 3, 29 September 2026
  • Sobha Central construction site, inspection photo 4, 29 September 2026

16 January 2026

0%

  • Sobha Central construction site, inspection photo 1, 16 January 2026
  • Sobha Central construction site, inspection photo 2, 16 January 2026

All 9 site photos, by inspection date

Context

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sobha Central?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sobha Central handover date?
The registered completion date is December 2031. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2055. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sobha Central?
Sobha Central was 2.4% built at the site inspection on 29 September 2026. The site has been inspected 2 times since January 2026. The Land Department took 9 site photos at its inspections.
Is Sobha Central delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2031.
Who is building Sobha Central?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Sobha Central?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.