Ellington Sands Ii construction progress

Ellington Sands Ii is 0.4% built at the Land Department inspection of June 2026. Developer Ellington Properties Development. Completion registered for December 2028.

0.4%

Built, at the Land Department site inspection of 5 June 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
February 2195
Construction started
October 2025
Registered with the Land Department
October 2025
Units
460
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
Ii إلينغتون ساندز
Land Department project number
4140
Land Department site inspections
2

Schedule

Between October 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around February 2195, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

5 June 2026

0.4%+0.4 pts

  • Ellington Sands Ii construction site, Land Department inspection photo 1, 5 June 2026
  • Ellington Sands Ii construction site, Land Department inspection photo 2, 5 June 2026
  • Ellington Sands Ii construction site, Land Department inspection photo 3, 5 June 2026
  • Ellington Sands Ii construction site, Land Department inspection photo 4, 5 June 2026

13 October 2025

0%

  • Ellington Sands Ii construction site, Land Department inspection photo 1, 13 October 2025
  • Ellington Sands Ii construction site, Land Department inspection photo 2, 13 October 2025

All 6 site photos, by inspection date

Context

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Ellington Sands Ii?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Ellington Sands Ii be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around February 2195. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Ellington Sands Ii is built?
0.4%, measured at the Land Department site inspection on 5 June 2026. The Land Department engineers have inspected the site 2 times since October 2025.
Is Ellington Sands Ii delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Ellington Sands Ii?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Ellington Sands Ii?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.