Ellington Sands I construction progress

The registered completion date for Ellington Sands I is December 2028. At the last site inspection, in June 2026, it was 0.4% built. The developer is Ellington Properties Development.

0.4%

Built, at the site inspection of 5 June 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
September 2199
Construction started
October 2025
First registered
October 2025
Units
471
Escrow bank
Commercial Bank of Dubai
Name in Arabic
I إلينغتون ساندز
Project number
4139
Site inspections
2

Schedule

Between October 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around September 2199, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 June 2026

0.4%+0.4 pts

  • Ellington Sands I construction site, inspection photo 1, 5 June 2026
  • Ellington Sands I construction site, inspection photo 2, 5 June 2026
  • Ellington Sands I construction site, inspection photo 3, 5 June 2026
  • Ellington Sands I construction site, inspection photo 4, 5 June 2026

13 October 2025

0%

  • Ellington Sands I construction site, inspection photo 1, 13 October 2025
  • Ellington Sands I construction site, inspection photo 2, 13 October 2025

All 6 site photos, by inspection date

Context

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Ellington Sands I?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ellington Sands I handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2199. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ellington Sands I?
Ellington Sands I was 0.4% built at the site inspection on 5 June 2026. The site has been inspected 2 times since October 2025. The Land Department took 6 site photos at its inspections.
Is Ellington Sands I delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Ellington Sands I?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Ellington Sands I?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.