Eaton Square construction progress

The registered completion date for Eaton Square is June 2028. At the last site inspection, in July 2026, it was 5.4% built. The developer is Ellington Properties Development.

5.4%

Built, at the site inspection of 20 July 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
August 2036
Construction started
December 2025
First registered
January 2026
Units
24
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
إيتون سكوير
Project number
4301
Site inspections
2

Schedule

Between December 2025 and July 2026 the site added about 0.8 points a month. At that rate it would finish around August 2036, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 July 2026

5.4%+5.4 pts

  • Eaton Square construction site, inspection photo 1, 20 July 2026
  • Eaton Square construction site, inspection photo 2, 20 July 2026
  • Eaton Square construction site, inspection photo 3, 20 July 2026
  • Eaton Square construction site, inspection photo 4, 20 July 2026

22 December 2025

0%

  • Eaton Square construction site, inspection photo 1, 22 December 2025
  • Eaton Square construction site, inspection photo 2, 22 December 2025

All 6 site photos, by inspection date

Context

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Eaton Square?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Eaton Square handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Eaton Square?
Eaton Square was 5.4% built at the site inspection on 20 July 2026. The site has been inspected 2 times since December 2025. The Land Department took 6 site photos at its inspections.
Is Eaton Square delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Eaton Square?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Eaton Square?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.