Eaton Square construction progress
The registered completion date for Eaton Square is June 2028. At the last site inspection, in July 2026, it was 5.4% built. The developer is Ellington Properties Development.
5.4%
Built, at the site inspection of 20 July 2026
Running behind its date
- Registered completion date
- June 2028
- Finish at recent pace
- August 2036
- Construction started
- December 2025
- First registered
- January 2026
- Developer
- Ellington Properties Development
- Units
- 24
- Escrow bank
- Al Ahli Bank of Kuwait
- Name in Arabic
- إيتون سكوير
- Project number
- 4301
- Site inspections
- 2
Schedule
Between December 2025 and July 2026 the site added about 0.8 points a month. At that rate it would finish around August 2036, more than three months after its registered date of June 2028.
Site inspections
20 July 2026
5.4%+5.4 pts
22 December 2025
0%
Context
Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.
Own a unit in Eaton Square?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Eaton Square handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Eaton Square?
- Eaton Square was 5.4% built at the site inspection on 20 July 2026. The site has been inspected 2 times since December 2025. The Land Department took 6 site photos at its inspections.
- Is Eaton Square delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Eaton Square?
- The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Eaton Square?
- Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The PortmanAlso by Ellington Properties Development. 79%, Due September 2025, passed.
- The HighburyAlso by Ellington Properties Development. 80%.
- Uh West By EllingtonAlso by Ellington Properties Development. 84%, Due March 2026, passed.
- Uh East By EllingtonAlso by Ellington Properties Development. 63%, Due March 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.