Aristo construction progress

The registered completion date for Aristo is December 2028. At the last site inspection, in July 2026, it was 0.1% built. The developer is Oksa Developer.

0.1%

Built, at the site inspection of 14 July 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
October 3175
Construction started
December 2025
First registered
December 2025
Developer
Oksa Developer
Units
66
Escrow bank
Ajman Bank
Name in Arabic
اريستو
Project number
4182
Site inspections
2

Schedule

Between November 2025 and July 2026 the site added about 0.0 points a month. At that rate it would finish around October 3175, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 July 2026

0.1%+0.1 pts

  • Aristo construction site, inspection photo 1, 14 July 2026
  • Aristo construction site, inspection photo 2, 14 July 2026
  • Aristo construction site, inspection photo 3, 14 July 2026
  • Aristo construction site, inspection photo 4, 14 July 2026

4 November 2025

0%

  • Aristo construction site, inspection photo 1, 4 November 2025
  • Aristo construction site, inspection photo 2, 4 November 2025
  • Aristo construction site, inspection photo 3, 4 November 2025

All 7 site photos, by inspection date

Context

Oksa Developer has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Aristo?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Aristo handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 3175. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Aristo?
Aristo was 0.1% built at the site inspection on 14 July 2026. The site has been inspected 2 times since November 2025. The Land Department took 7 site photos at its inspections.
Is Aristo delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Aristo?
The registered developer is Oksa Developer. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Aristo?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.