Orchid Residence 1 construction progress

Orchid Residence 1 in Dubai South Residential District is 48% built at the Land Department inspection of May 2026. Developer Orchid Living Real Estate. Completion registered for March 2026.

48%

Built, at the Land Department site inspection of 19 May 2026

6 months past its registered completion date

Completion date (Land Department)
March 2026
Finish at recent pace
January 2029
Construction started
July 2024
Registered with the Land Department
November 2025
Developer
Orchid Living Real Estate
Units
44
Escrow bank
Mashreq Bank
Name in Arabic
أوركيد ريزيدنس 1
Land Department project number
4054
Land Department site inspections
2

Schedule

Orchid Residence 1 was registered to complete in March 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around January 2029.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

19 May 2026

48%+11 pts

  • Orchid Residence 1 construction site, Land Department inspection photo 1, 19 May 2026
  • Orchid Residence 1 construction site, Land Department inspection photo 2, 19 May 2026
  • Orchid Residence 1 construction site, Land Department inspection photo 3, 19 May 2026
  • Orchid Residence 1 construction site, Land Department inspection photo 4, 19 May 2026

17 October 2025

37%

  • Orchid Residence 1 construction site, Land Department inspection photo 1, 17 October 2025
  • Orchid Residence 1 construction site, Land Department inspection photo 2, 17 October 2025
  • Orchid Residence 1 construction site, Land Department inspection photo 3, 17 October 2025
  • Orchid Residence 1 construction site, Land Department inspection photo 4, 17 October 2025

All 15 site photos, by inspection date

Context

Dubai South Residential District has 40 projects under construction, 40% built on average.

Own a unit in Orchid Residence 1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Orchid Residence 1 be completed?
The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around January 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Orchid Residence 1 is built?
48%, measured at the Land Department site inspection on 19 May 2026. The Land Department engineers have inspected the site 2 times since October 2025.
Is Orchid Residence 1 delayed?
Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
Who is building Orchid Residence 1?
The registered developer is Orchid Living Real Estate.
Which bank holds the escrow account for Orchid Residence 1?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.