Orchid Residence 1 construction progress

Orchid Residence 1 in Dubai South Residential District was registered to complete in March 2026 and is still under construction. At the last site inspection, in May 2026, it was 48% built. The developer is Orchid Living Real Estate.

48%

Built, at the site inspection of 19 May 2026

8 months past its registered completion date

Registered completion date
March 2026
Finish at recent pace
January 2029
Construction started
July 2024
First registered
November 2025
Developer
Orchid Living Real Estate
Units
44
Escrow bank
Mashreq Bank
Name in Arabic
أوركيد ريزيدنس 1
Project number
4054
Site inspections
2

Schedule

Orchid Residence 1 was registered to complete in March 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around January 2029.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 May 2026

48%+11 pts

  • Orchid Residence 1 construction site, inspection photo 1, 19 May 2026
  • Orchid Residence 1 construction site, inspection photo 2, 19 May 2026
  • Orchid Residence 1 construction site, inspection photo 3, 19 May 2026
  • Orchid Residence 1 construction site, inspection photo 4, 19 May 2026

17 October 2025

37%

  • Orchid Residence 1 construction site, inspection photo 1, 17 October 2025
  • Orchid Residence 1 construction site, inspection photo 2, 17 October 2025
  • Orchid Residence 1 construction site, inspection photo 3, 17 October 2025
  • Orchid Residence 1 construction site, inspection photo 4, 17 October 2025

All 15 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in Orchid Residence 1?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Orchid Residence 1 handover date?
The registered completion date was March 2026, and the register still lists Orchid Residence 1 as under construction. At the pace of its recent inspections the site would reach 100% around January 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Orchid Residence 1?
Orchid Residence 1 was 48% built at the site inspection on 19 May 2026. The site has been inspected 2 times since October 2025. The Land Department took 15 site photos at its inspections.
Is Orchid Residence 1 delayed?
Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
Who is building Orchid Residence 1?
The registered developer is Orchid Living Real Estate.
Which bank holds the escrow account for Orchid Residence 1?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.