Livia Residence construction progress
The registered completion date for Livia Residence in Dubai South Residential District is April 2027. At the last site inspection, in November 2026, it was 23% built. The developer is Barco Properties Development.
23%
Built, at the site inspection of 10 November 2026
Running behind its date
- Registered completion date
- April 2027
- Finish at recent pace
- September 2029
- Construction started
- June 2025
- First registered
- August 2025
- Developer
- Barco Properties Development
- Community
- Dubai South Residential District
- Units
- 71
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- ليفيا رزيدينسيز
- Project number
- 3687
- Site inspections
- 5
Schedule
Between January 2026 and November 2026 the site added about 2.3 points a month. At that rate it would finish around September 2029, more than three months after its registered date of April 2027.
Site inspections
10 November 2026
23%+8.3 pts
30 July 2026
15%+5.3 pts
23 April 2026
9.3%+7.9 pts
27 January 2026
1.4%+1.4 pts
16 April 2025
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Own a unit in Livia Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Livia Residence handover date?
- The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Livia Residence?
- Livia Residence was 23% built at the site inspection on 10 November 2026. The site has been inspected 5 times since April 2025. The Land Department took 23 site photos at its inspections.
- Is Livia Residence delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
- Who is building Livia Residence?
- The registered developer is Barco Properties Development.
- Which bank holds the escrow account for Livia Residence?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.