Altair 52 construction progress

The registered completion date for Altair 52 in Dubai South Residential District is December 2027. At the last site inspection, in September 2026, it was 10% built. The developer is Acube Abodes Real Estate Development.

10%

Built, at the site inspection of 24 September 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
June 2032
Construction started
December 2025
First registered
September 2025
Developer
Acube Abodes Real Estate Development
Units
52
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
الطير 52
Project number
3657
Site inspections
3

Schedule

Between March 2026 and September 2026 the site added about 1.3 points a month. At that rate it would finish around June 2032, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 September 2026

10%+7.7 pts

  • Altair 52 construction site, inspection photo 1, 24 September 2026
  • Altair 52 construction site, inspection photo 2, 24 September 2026
  • Altair 52 construction site, inspection photo 3, 24 September 2026
  • Altair 52 construction site, inspection photo 4, 24 September 2026

27 March 2026

2.3%+2.3 pts

  • Altair 52 construction site, inspection photo 1, 27 March 2026
  • Altair 52 construction site, inspection photo 2, 27 March 2026
  • Altair 52 construction site, inspection photo 3, 27 March 2026
  • Altair 52 construction site, inspection photo 4, 27 March 2026

10 June 2025

0%

  • Altair 52 construction site, inspection photo 1, 10 June 2025
  • Altair 52 construction site, inspection photo 2, 10 June 2025

All 12 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Own a unit in Altair 52?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Altair 52 handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Altair 52?
Altair 52 was 10% built at the site inspection on 24 September 2026. The site has been inspected 3 times since June 2025. The Land Department took 12 site photos at its inspections.
Is Altair 52 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Altair 52?
The registered developer is Acube Abodes Real Estate Development.
Which bank holds the escrow account for Altair 52?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.