Altair 52 construction progress

Altair 52 in Dubai South Residential District is 10% built at the Land Department inspection of September 2026. Developer Acube Abodes Real Estate Development. Completion registered for December 2027.

10%

Built, at the Land Department site inspection of 24 September 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
June 2032
Construction started
December 2025
Registered with the Land Department
September 2025
Developer
Acube Abodes Real Estate Development
Units
52
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
الطير 52
Land Department project number
3657
Land Department site inspections
3

Schedule

Between March 2026 and September 2026 the site added about 1.3 points a month. At that rate it would finish around June 2032, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

24 September 2026

10%+7.7 pts

  • Altair 52 construction site, Land Department inspection photo 1, 24 September 2026
  • Altair 52 construction site, Land Department inspection photo 2, 24 September 2026
  • Altair 52 construction site, Land Department inspection photo 3, 24 September 2026
  • Altair 52 construction site, Land Department inspection photo 4, 24 September 2026

27 March 2026

2.3%+2.3 pts

  • Altair 52 construction site, Land Department inspection photo 1, 27 March 2026
  • Altair 52 construction site, Land Department inspection photo 2, 27 March 2026
  • Altair 52 construction site, Land Department inspection photo 3, 27 March 2026
  • Altair 52 construction site, Land Department inspection photo 4, 27 March 2026

10 June 2025

0%

  • Altair 52 construction site, Land Department inspection photo 1, 10 June 2025
  • Altair 52 construction site, Land Department inspection photo 2, 10 June 2025

All 12 site photos, by inspection date

Context

Dubai South Residential District has 40 projects under construction, 40% built on average.

Own a unit in Altair 52?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Altair 52 be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around June 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Altair 52 is built?
10%, measured at the Land Department site inspection on 24 September 2026. The Land Department engineers have inspected the site 3 times since June 2025.
Is Altair 52 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Altair 52?
The registered developer is Acube Abodes Real Estate Development.
Which bank holds the escrow account for Altair 52?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.