Nova Tower construction progress
Nova Tower in Dubai Science Park was registered to complete in September 2026 and is still under construction. At the last site inspection, in November 2026, it was 50% built. The developer is Alansari Real Estate Development.
50%
Built, at the site inspection of 16 November 2026
2 months past its registered completion date
- Registered completion date
- September 2026
- Finish at recent pace
- February 2028
- Construction started
- December 2024
- First registered
- August 2025
- Developer
- Alansari Real Estate Development
- Community
- Dubai Science Park
- Units
- 134
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- برج نوفا
- Project number
- 3870
- Site inspections
- 5
Schedule
Nova Tower was registered to complete in September 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around February 2028.
Site inspections
16 November 2026
50%+10 pts
3 August 2026
40%+14 pts
24 April 2026
26%+8.6 pts
19 January 2026
17%+10 pts
14 July 2025
7.5%
Context
Dubai Science Park has 10 projects under construction, 43% built on average.
Own a unit in Nova Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Nova Tower handover date?
- The registered completion date was September 2026, and the register still lists Nova Tower as under construction. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Nova Tower?
- Nova Tower was 50% built at the site inspection on 16 November 2026. The site has been inspected 5 times since July 2025. The Land Department took 42 site photos at its inspections.
- Is Nova Tower delayed?
- Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
- Who is building Nova Tower?
- The registered developer is Alansari Real Estate Development.
- Which bank holds the escrow account for Nova Tower?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Vincitore Aqua DimoreNearby in Dubai Science Park. 14%.
- Binghatti HillsNearby in Dubai Science Park. 90%.
- Vincitore Aqua FloraNearby in Dubai Science Park. 1.3%, Due June 2028.
- Empire LivingsNearby in Dubai Science Park. 13%, Due November 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)