Nova Tower construction progress

Nova Tower in Dubai Science Park was registered to complete in September 2026 and is still under construction. At the last site inspection, in November 2026, it was 50% built. The developer is Alansari Real Estate Development.

50%

Built, at the site inspection of 16 November 2026

2 months past its registered completion date

Registered completion date
September 2026
Finish at recent pace
February 2028
Construction started
December 2024
First registered
August 2025
Developer
Alansari Real Estate Development
Units
134
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
برج نوفا
Project number
3870
Site inspections
5

Schedule

Nova Tower was registered to complete in September 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around February 2028.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 November 2026

50%+10 pts

  • Nova Tower construction site, inspection photo 1, 16 November 2026
  • Nova Tower construction site, inspection photo 2, 16 November 2026
  • Nova Tower construction site, inspection photo 3, 16 November 2026
  • Nova Tower construction site, inspection photo 4, 16 November 2026

3 August 2026

40%+14 pts

  • Nova Tower construction site, inspection photo 1, 3 August 2026
  • Nova Tower construction site, inspection photo 2, 3 August 2026
  • Nova Tower construction site, inspection photo 3, 3 August 2026
  • Nova Tower construction site, inspection photo 4, 3 August 2026

24 April 2026

26%+8.6 pts

  • Nova Tower construction site, inspection photo 1, 24 April 2026
  • Nova Tower construction site, inspection photo 2, 24 April 2026
  • Nova Tower construction site, inspection photo 3, 24 April 2026
  • Nova Tower construction site, inspection photo 4, 24 April 2026

19 January 2026

17%+10 pts

  • Nova Tower construction site, inspection photo 1, 19 January 2026
  • Nova Tower construction site, inspection photo 2, 19 January 2026
  • Nova Tower construction site, inspection photo 3, 19 January 2026
  • Nova Tower construction site, inspection photo 4, 19 January 2026

14 July 2025

7.5%

  • Nova Tower construction site, inspection photo 1, 14 July 2025
  • Nova Tower construction site, inspection photo 2, 14 July 2025
  • Nova Tower construction site, inspection photo 3, 14 July 2025
  • Nova Tower construction site, inspection photo 4, 14 July 2025

All 42 site photos, by inspection date

Context

Dubai Science Park has 10 projects under construction, 43% built on average.

Own a unit in Nova Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Nova Tower handover date?
The registered completion date was September 2026, and the register still lists Nova Tower as under construction. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Nova Tower?
Nova Tower was 50% built at the site inspection on 16 November 2026. The site has been inspected 5 times since July 2025. The Land Department took 42 site photos at its inspections.
Is Nova Tower delayed?
Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
Who is building Nova Tower?
The registered developer is Alansari Real Estate Development.
Which bank holds the escrow account for Nova Tower?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.