Talea construction progress
The registered completion date for Talea in Dubai Maritime City is June 2028. At the last site inspection, in November 2026, it was 4.7% built. The developer is Manarola Real Estate Developments.
4.7%
Built, at the site inspection of 2 November 2026
Running behind its date
- Registered completion date
- June 2028
- Finish at recent pace
- February 2039
- Construction started
- March 2026
- First registered
- July 2025
- Developer
- Manarola Real Estate Developments
- Community
- Dubai Maritime City
- Units
- 354
- Escrow bank
- Emirates NBD
- Name in Arabic
- تاليا
- Project number
- 3869
- Site inspections
- 4
Schedule
Between March 2026 and November 2026 the site added about 0.6 points a month. At that rate it would finish around February 2039, more than three months after its registered date of June 2028.
Site inspections
2 November 2026
4.7%+4.7 pts
24 March 2026
0%
16 October 2025
0%+0.0 pts
9 July 2025
0%
Context
Dubai Maritime City has 23 projects under construction, 32% built on average.
Own a unit in Talea?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Talea handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Talea?
- Talea was 4.7% built at the site inspection on 2 November 2026. The site has been inspected 4 times since July 2025. The Land Department took 10 site photos at its inspections.
- Is Talea delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Talea?
- The registered developer is Manarola Real Estate Developments.
- Which bank holds the escrow account for Talea?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Harbour LightsNearby in Dubai Maritime City. 72%, Due May 2027.
- Mar CasaNearby in Dubai Maritime City. 67%, Due October 2026, passed.
- Aria By BeyondNearby in Dubai Maritime City. 85%, Due January 2026, passed.
- Coral ReefNearby in Dubai Maritime City. 33%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)