Talea construction progress

The registered completion date for Talea in Dubai Maritime City is June 2028. At the last site inspection, in November 2026, it was 4.7% built. The developer is Manarola Real Estate Developments.

4.7%

Built, at the site inspection of 2 November 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
February 2039
Construction started
March 2026
First registered
July 2025
Developer
Manarola Real Estate Developments
Units
354
Escrow bank
Emirates NBD
Name in Arabic
تاليا
Project number
3869
Site inspections
4

Schedule

Between March 2026 and November 2026 the site added about 0.6 points a month. At that rate it would finish around February 2039, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 November 2026

4.7%+4.7 pts

  • Talea construction site, inspection photo 1, 2 November 2026
  • Talea construction site, inspection photo 2, 2 November 2026
  • Talea construction site, inspection photo 3, 2 November 2026
  • Talea construction site, inspection photo 4, 2 November 2026

24 March 2026

0%

  • Talea construction site, inspection photo 1, 24 March 2026
  • Talea construction site, inspection photo 2, 24 March 2026

16 October 2025

0%+0.0 pts

  • Talea construction site, inspection photo 1, 16 October 2025
  • Talea construction site, inspection photo 2, 16 October 2025

9 July 2025

0%

  • Talea construction site, inspection photo 1, 9 July 2025

All 10 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 32% built on average.

Own a unit in Talea?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Talea handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Talea?
Talea was 4.7% built at the site inspection on 2 November 2026. The site has been inspected 4 times since July 2025. The Land Department took 10 site photos at its inspections.
Is Talea delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Talea?
The registered developer is Manarola Real Estate Developments.
Which bank holds the escrow account for Talea?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.