Skip to content

Soulever' By Beyond construction progress

The registered completion date for Soulever' By Beyond in Dubai Maritime City is December 2028. At the last site inspection, in November 2026, it was 1.6% built. The developer is Beyond 1 Real Estate Development.

1.6%

Built, at the site inspection of 19 November 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
March 2061
Construction started
March 2026
First registered
September 2025
Developer
Beyond 1 Real Estate Development
Units
517
Escrow bank
Emirates NBD
Name in Arabic
سوليفر من بيوند
Project number
4084
Site inspections
3

Schedule

Between April 2026 and November 2026 the site added about 0.2 points a month. At that rate it would finish around March 2061, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 November 2026

1.6%+1.6 pts

  • Soulever' By Beyond construction site, inspection photo 1, 19 November 2026
  • Soulever' By Beyond construction site, inspection photo 2, 19 November 2026
  • Soulever' By Beyond construction site, inspection photo 3, 19 November 2026
  • Soulever' By Beyond construction site, inspection photo 4, 19 November 2026

24 April 2026

0%

  • Soulever' By Beyond construction site, inspection photo 1, 24 April 2026
  • Soulever' By Beyond construction site, inspection photo 2, 24 April 2026

22 September 2025

0%

  • Soulever' By Beyond construction site, inspection photo 1, 22 September 2025
  • Soulever' By Beyond construction site, inspection photo 2, 22 September 2025

All 10 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 32% built on average.

Own a unit in Soulever' By Beyond?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Soulever' By Beyond handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2061. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Soulever' By Beyond?
Soulever' By Beyond was 1.6% built at the site inspection on 19 November 2026. The site has been inspected 3 times since September 2025. The Land Department took 10 site photos at its inspections.
Is Soulever' By Beyond delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Soulever' By Beyond?
The registered developer is Beyond 1 Real Estate Development.
Which bank holds the escrow account for Soulever' By Beyond?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.