Sensia construction progress
The registered completion date for Sensia in Dubai Maritime City is March 2029. At the last site inspection, in October 2026, it was 18% built. The developer is Sensia Land Real Estate Development.
18%
Built, at the site inspection of 1 October 2026
Running behind its date
- Registered completion date
- March 2029
- Finish at recent pace
- March 2032
- Construction started
- September 2025
- First registered
- February 2025
- Developer
- Sensia Land Real Estate Development
- Community
- Dubai Maritime City
- Units
- 276
- Escrow bank
- Emirates NBD
- Name in Arabic
- سنسيا
- Project number
- 3577
- Site inspections
- 6
Schedule
Between October 2025 and October 2026 the site added about 1.2 points a month. At that rate it would finish around March 2032, more than three months after its registered date of March 2029.
Site inspections
1 October 2026
18%+9.4 pts
7 May 2026
8.1%+3.4 pts
28 January 2026
4.7%+1.2 pts
24 October 2025
3.5%+3.4 pts
29 July 2025
0.1%+0.1 pts
25 February 2025
0%
Context
Dubai Maritime City has 23 projects under construction, 32% built on average.
Own a unit in Sensia?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sensia handover date?
- The registered completion date is March 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sensia?
- Sensia was 18% built at the site inspection on 1 October 2026. The site has been inspected 6 times since February 2025. The Land Department took 27 site photos at its inspections.
- Is Sensia delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
- Who is building Sensia?
- The registered developer is Sensia Land Real Estate Development.
- Which bank holds the escrow account for Sensia?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Harbour LightsNearby in Dubai Maritime City. 72%, Due May 2027.
- Mar CasaNearby in Dubai Maritime City. 67%, Due October 2026, passed.
- Aria By BeyondNearby in Dubai Maritime City. 85%, Due January 2026, passed.
- Coral ReefNearby in Dubai Maritime City. 33%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

