Saria construction progress

The registered completion date for Saria in Dubai Maritime City is October 2027. At the last site inspection, in October 2026, it was 31% built. The developer is Veris Residences Real Estate Development.

31%

Built, at the site inspection of 1 October 2026

Running behind its date

Registered completion date
October 2027
Finish at recent pace
June 2029
Construction started
November 2024
First registered
September 2024
Developer
Veris Residences Real Estate Development
Units
372
Escrow bank
Emirates NBD
Name in Arabic
سارية
Project number
3115
Site inspections
7

Schedule

Between October 2025 and October 2026 the site added about 2.1 points a month. At that rate it would finish around June 2029, more than three months after its registered date of October 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 October 2026

31%+14 pts

  • Saria construction site, inspection photo 1, 1 October 2026
  • Saria construction site, inspection photo 2, 1 October 2026
  • Saria construction site, inspection photo 3, 1 October 2026
  • Saria construction site, inspection photo 4, 1 October 2026

7 May 2026

17%+6.6 pts

  • Saria construction site, inspection photo 1, 7 May 2026
  • Saria construction site, inspection photo 2, 7 May 2026
  • Saria construction site, inspection photo 3, 7 May 2026
  • Saria construction site, inspection photo 4, 7 May 2026

28 January 2026

10%+3.2 pts

  • Saria construction site, inspection photo 1, 28 January 2026
  • Saria construction site, inspection photo 2, 28 January 2026
  • Saria construction site, inspection photo 3, 28 January 2026
  • Saria construction site, inspection photo 4, 28 January 2026

24 October 2025

7.1%+0.8 pts

  • Saria construction site, inspection photo 1, 24 October 2025
  • Saria construction site, inspection photo 2, 24 October 2025
  • Saria construction site, inspection photo 3, 24 October 2025
  • Saria construction site, inspection photo 4, 24 October 2025

29 July 2025

6.3%+5.7 pts

  • Saria construction site, inspection photo 1, 29 July 2025
  • Saria construction site, inspection photo 2, 29 July 2025
  • Saria construction site, inspection photo 3, 29 July 2025
  • Saria construction site, inspection photo 4, 29 July 2025

14 April 2025

0.6%+0.6 pts

  • Saria construction site, inspection photo 1, 14 April 2025
  • Saria construction site, inspection photo 2, 14 April 2025
  • Saria construction site, inspection photo 3, 14 April 2025
  • Saria construction site, inspection photo 4, 14 April 2025

8 July 2024

0%

  • Saria construction site, inspection photo 1, 8 July 2024
  • Saria construction site, inspection photo 2, 8 July 2024
  • Saria construction site, inspection photo 3, 8 July 2024

All 34 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 32% built on average.

Own a unit in Saria?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Saria handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Saria?
Saria was 31% built at the site inspection on 1 October 2026. The site has been inspected 7 times since July 2024. The Land Department took 34 site photos at its inspections.
Is Saria delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Saria?
The registered developer is Veris Residences Real Estate Development.
Which bank holds the escrow account for Saria?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.